HomeMy WebLinkAbout020607 Virginia Aquarium #1Virginia Aquarium and Marine Science Center · Changing Functional Use of Building · Over Water · Keep Facility Open · Accessibility to Site · High Risk · City Used Same AlE as Foundation · City Pre-qualified Contractors · Foundation used City Contractor · Three Cost Estimates Bid Opening December 7, 2006 •Cost Estimate $7.4M •Low Bid $12.6M •CSP Did Not Assign the Same Value to the Project Risks as the Contractors Options: •Transfer $5.6M From Other Projects and Award Contract •Use a Different Procurement Method •Start Over/Re-Design