HomeMy WebLinkAbout031108 Town CenterMarch 11, 2008
PHASE IV-TOWN CENTER
Block 2
(Beacon Building)
1
Site of
New
Tower
2
3
Town Center Development Recap
Town Center Development Recap
Phase I –February 2000
Phase I –February 2000
?
?
Office Tower (Block 4)
Office Tower (Block 4)
?
?
Towne Bank (Block 5)
Towne Bank (Block 5)
?
?
Hilton Garden Inn (Block 5 –176 rooms)
Hilton Garden Inn (Block 5 –176 rooms)
?
?
Phase II –June 2003
Phase II –June 2003
?
?
342-unit Cosmopolitan Apartments (Block 10)
342-unit Cosmopolitan Apartments (Block 10)
?
?
Dick’s Sporting Goods (Block 12)
Dick’s Sporting Goods (Block 12)
?
?
2-story retail/entertainment (Block 8 –Bravo!, Comedy Club, Ruth’s
2-story retail/entertainment (Block 8 –Bravo!, Comedy Club, Ruth’s
?
?
Chris Steak House)
Chris Steak House)
Restaurants (Block 3 –Cheesecake Factory, Keegan’s)
Restaurants (Block 3 –Cheesecake Factory, Keegan’s)
?
?
Phase III –September 2005
Phase III –September 2005
?
?
37-story Westin Hotel/condominium tower (Block 7)
37-story Westin Hotel/condominium tower (Block 7)
?
?
236-room full service hotel (Floors 5 –15)
236-room full service hotel (Floors 5 –15)
?
?
119 condos (Floors 16 –36) + penthouse/common area
119 condos (Floors 16 –36) + penthouse/common area
?
?
56 condominiums, 14,000 sq. ft. ground floor retail (Block 6)
56 condominiums, 14,000 sq. ft. ground floor retail (Block 6)
?
?
Office Building, 97,040 sq. ft. (Block 5 –FY-10)
Office Building, 97,040 sq. ft. (Block 5 –FY-10)
?
?
4
VBDA Support -TIF Funded
VBDA Support -TIF Funded
Phase I
Phase I
?
?
Parking Garage (Block 4)
Parking Garage (Block 4)
?
?
1,284 spaces
1,284 spaces
?
?
Plaza Land (Block 8)
Plaza Land (Block 8)
?
?
Phase II
Phase II
?
?
Parking Garage (Block 10)
Parking Garage (Block 10)
?
?
851 spaces
851 spaces
?
?
Parking Garage (Block 12)
Parking Garage (Block 12)
?
?
574 spaces (269 are for theatre -CIP funded)
574 spaces (269 are for theatre -CIP funded)
?
?
Phase III
Phase III
?
?
Parking Garage (Block 7)
Parking Garage (Block 7)
?
?
735 public spaces (additional 212 for condos –Developer financed)
735 public spaces (additional 212 for condos –Developer financed)
?
?
Pedestrian Bridge (connects garages in Block 12 to Block 7)
Pedestrian Bridge (connects garages in Block 12 to Block 7)
?
?
Meeting Room/Conference Facility (Block 7)
Meeting Room/Conference Facility (Block 7)
?
?
5
Scope of Improvements
Scope of Improvements
Phase IV
Phase IV
BLOCK TWO
BLOCK TWO
•
•
Single Block, Multi-facility, Mixed-use Development
Single Block, Multi-facility, Mixed-use Development
•
•
21 Stories –364,000 sq. ft.
21 Stories –364,000 sq. ft.
•
•
Main Lobby, Retail (First Floor) –34,000 sq. ft.
Main Lobby, Retail (First Floor) –34,000 sq. ft.
•
•
Parking Garage, 650 Spaces (8 levels)
Parking Garage, 650 Spaces (8 levels)
•
•
Office Space –330,000 sq. ft.
Office Space –330,000 sq. ft.
•
•
6
Developer Obligations
Developer Obligations
Phase IV
Phase IV
Purchase land required for development and
Purchase land required for development and
?
?
construction of Phase IV Tower from Authority
construction of Phase IV Tower from Authority
(at Authority’s cost of acquisition)
(at Authority’s cost of acquisition)
Construct all improvements on Block 2
Construct all improvements on Block 2
?
?
Estimated Private Investment $72 -$82 million
Estimated Private Investment $72 -$82 million
?
?
7
VBDA Obligations
VBDA Obligations
Phase IV
Phase IV
Purchase 650-Space Parking Garage
Purchase 650-Space Parking Garage
?
?
Developer to construct
Developer to construct
?
?
Estimated cost : $22-28 million
Estimated cost : $22-28 million
?
?
Price determined same manner as Block 10
Price determined same manner as Block 10
?
?
(Cosmopolitan) and Block 12 (Dick’s) garages
(Cosmopolitan) and Block 12 (Dick’s) garages
Number of spacesx Per space price(from construction
Number of spacesx Per space price(from construction
?
?
bids)
bids)
Price will be known before execution of Phase IV
Price will be known before execution of Phase IV
?
?
Development Agreement.
Development Agreement.
To be paid from TIF revenues
To be paid from TIF revenues
?
?
(continued…)
(continued…)
8
VBDA Obligations
VBDA Obligations
Phase IV
Phase IV
(cont.)
Pay for Infrastructure Improvements on Block 2
Pay for Infrastructure Improvements on Block 2
?
?
Estimated Cost: $650,000 -$850,000
Estimated Cost: $650,000 -$850,000
?
?
Lease 1 floor in new 21-story Main Office Tower
Lease 1 floor in new 21-story Main Office Tower
?
?
Leased Area: ~ 25,000 square feet
Leased Area: ~ 25,000 square feet
?
?
VBDA’s rent
VBDA’s rent
?
?
~ $30.50 to $31.00/SF or $762,500-$775,000 per year
~ $30.50 to $31.00/SF or $762,500-$775,000 per year
?
?
Lowest rent in tower, other than anchor tenant
Lowest rent in tower, other than anchor tenant
?
?
9
Additional Terms
Additional Terms
Phase IV
Phase IV
Modify Option Land Agreement to permit purchase of
Modify Option Land Agreement to permit purchase of
?
?
Block 2 (Beacon) before Block 12 Commercial Unit
Block 2 (Beacon) before Block 12 Commercial Unit
Developer may lease from VBDA up to 10% of
Developer may lease from VBDA up to 10% of
?
?
parking spaces under long-term lease (so long as
parking spaces under long-term lease (so long as
approved by bond counsel)
approved by bond counsel)
Garage acquisition and operation will mirror existing
Garage acquisition and operation will mirror existing
?
?
garages at Town Center
garages at Town Center
Phase IV is contingent on completion of Beacon land
Phase IV is contingent on completion of Beacon land
?
?
exchange
exchange
10
Notes: Summary of Phase IV Costs
Notes: Summary of Phase IV Costs
(millions)
(millions)
Public Investment
Public Investment
?
?
Block 2 garage -$22.0 -$28.0
Block 2 garage -$22.0 -$28.0
?
?
Block 2 Infrastructure -$0.650 -$0.850
Block 2 Infrastructure -$0.650 -$0.850
?
?
TOTAL PUBLIC -$22.65 -$28.85
TOTAL PUBLIC -$22.65 -$28.85
Private Investment
Private Investment
?
?
Block 2 Tower -$72.0 -$82.0
Block 2 Tower -$72.0 -$82.0
?
?
TOTAL PRIVATE -$72.0 -$82.0
TOTAL PRIVATE -$72.0 -$82.0
11
Summary of Public and Private Investments
Phases I, II, III & IV
(millions)
March 2008
Project ElementPhase IPhase IIPhase IIIPhase IVTotal
Project ElementPhase IPhase IIPhase IIIPhase IVTotal
PUBLIC INVESTMENT*
PUBLIC INVESTMENT*
$29.3$25.8$28.5$22.7 -$28.9$106.3 -$112.5
$29.3$25.8$28.5$22.7 -$28.9$106.3 -$112.5
PRIVATE
PRIVATE
$95$97$220$72 -$82$484 -$494
$95$97$220$72 -$82$484 -$494
INVESTMENT
INVESTMENT
TOTAL INVESTMENT
TOTAL INVESTMENT
$124.3$122.8$248.5$94.7 -$110.9$590.3 -$606.5
$124.3$122.8$248.5$94.7 -$110.9$590.3 -$606.5
Public:Private Ratio
Public:Private Ratio
1 to 3.21 to 3.81 to 7.71 to 3.01 to 4.5
1 to 3.21 to 3.81 to 7.71 to 3.01 to 4.5
Includes garages and infrastructure
*
12
Business Taxes Generated Within the Core
Business Taxes Generated Within the Core
Area of the CBD South TIF District*
Area of the CBD South TIF District*
Type of Tax200520062007
Type of Tax200520062007
Business License $749,444$850,035$1,042,999
Business License $749,444$850,035$1,042,999
Business Property229,863348,014392,511
Business Property229,863348,014392,511
Trustee Taxes**1,677,8272,584,4852,749,749
Trustee Taxes**1,677,8272,584,4852,749,749
General Sales Taxes481,428534,363568,758
General Sales Taxes481,428534,363568,758
TOTAL$3,138,562$4,316,897$4,754,017
TOTAL$3,138,562$4,316,897$4,754,017
* Source: Commissioner of the Revenue
**Includes meal, admission, and hotel taxes; excludes utility taxes, which are difficult to
quantify.
Anticipated number of jobs in the Block 2 Tower = 1,500 –1,600
13
14
15
QUESTIONS?
16