Loading...
HomeMy WebLinkAbout100708 Indoor Sports FacilityPrincess Anne Athletic Development, LLC (PAAD) Status Report October 7, 2008 1 LANDSTOWN ROAD AERIAL VIEW OF VIRGINIA BEACH SPORTSPLEX 2 Jan 2007 CurrentReality CurrentReality 3 Timeline Timeline Sept 4, 2007 Council briefed on study. Council approves RFI. Oct 4, 2007 RFI advertised. Nov 26, 2007 Staff recommended two groups. Dec 11, 2007 Council briefed on RFI responses. Dec 21, 2007 Finances reviewed. Both firms OK’d. Feb 12, 2008 Council briefed on Redskins. RFI revised. Council briefed on interviews; approves Apr 21, 2008 negotiations with PAAD. Sep 9, 2008 Council briefed on term sheet. Council briefed on term sheet. Sep 23, 2008 4 Site Concept Site Concept $3,500,000 Infrastructure $6,475,000 Retail Complex $12,850,000 Field House $135,000 USFH Upgrade $1,060,000 SportsplexUpgrade 5 Field House Field House 6 Sportsplex Commons -Retail Sportsplex Commons -Retail 7 The Proposal The Proposal Construction of Private Sector Investment ? $12,850,000 166,000 ftindoor sports fieldhouse facility 2 ? 50,000 ftsports retail center –Sportsplex 2 $ 6,475,000 ? Commons Upgrade of ? Sportsplex (artificial turf and concession $ 1,060,000 ? upgrades) USFHA facility (spectator seating, video $ 135,000 ? towers, etc.) Infrastructure improvements ? $ 3,500,000 Access road ? Stormwater ponds ? Parking lot paving for all facilities ? $24,020,000 8 More Proposal Details More Proposal Details Two-year option to build six (6) lighted ? artificial turf fields Option to enclose Sportsplexfield during ? winter months Cost of future capital improvements/ ? replacements to be City responsibility for Sportsplexand USFH Field House and artificial turf fields can be ? built without retail center Management of Sportsplex and USFH ? facilities depends on retail center 9 Business Structure Business Structure 1. Master Developer with PAAD, LLC 1. Master Developer with PAAD, LLC Development Agreement for construction of ? infrastructure Timeframe for completion ? Construction standards ? Investment criteria defined ? Pond ? Parking ? Access Road ? 10 Business Structure Business Structure 2.Virginia Beach Field House, LLC 2.Virginia Beach Field House, LLC (Principals –John Wack, Tom Wack, & Cathy Wack, et al.) Ground Lease for Field House ? Construction of Field House with ? timeframe of completion (Nov 2009), construction standards and investment criteria Performance parameters and thresholds ? City profit sharing defined ? 13.9 acres ? Option on 23.6 acres for six (6) ? additional fields 11 Business Structure Business Structure 3.SportsplexCommons, LLC 3.SportsplexCommons, LLC (Principals –Paul Van & Chuck Thorton, et al.) Ground Lease for Retail Center ? Construction of Retail Center with timeframe of ? completion, construction standards and investment criteria Performance parameters and thresholds ? City profit sharing defined ? 4.Hometown Sports Management, LLC 4.Hometown Sports Management, LLC (Principals –Paul Van & Chuck Thorton, et al.) Management Agreements for Sportsplex& USFH ? Performance parameters and thresholds ? Types of usage allowed ? Still needs further negotiation ? City profit-sharing defined ? 12 Summary of Terms Summary of Terms I.Term20 years, with two 10-year renewal periods, at lessee option II.RentNominal for all land leased III.Management For Sportsplex and USFH Agreement IV.Incentive Paid by Annual performance grant for 10 Cityyears equal to real estate taxes paid V.Revenue Sharing General 5% of gross revenues over Received by Citya threshold level 13 Summary of Cash Flows to City Summary of Cash Flows to City First 20 Years The components of the net cash flow are as follows: Real Estate Taxes Paid to the City$ 7.5 million Incentive Grant Paid to PAAD (10 years) -3.2 million Revenue Sharing paid to the City3.0 million Cost Savings Sportsplex& USFH Operations12.0 million Total Cash Flows to the City$19.3 million Other Fiscal Impacts$47.4 million TOTAL $66.7 million 14 Timeline –Next Steps Timeline –Next Steps Public Presentation. Oct 7, 2008 Conditional Rezoning (from AG to B2) & Oct 8, 2008 Conditional Use Permit to Planning Commission. Open House at the Advanced Oct 30, 2008 Technology Center. Conditional Rezoning & Conditional Nov 25, 2008 Use Permit to Council. Complete negotiations with PAAD, LLC. Nov 30, 2008 Final Lease/Management Terms Dec 2, 2008 to Council for consideration. Feb, 2009 Construction begins. Nov, 2009 Facility Open. 15 Benefits of the Project Benefits of the Project Community Recreation amenity that would not ? happen otherwise Opportunity to improve and expand use of existing ? Sportsplexand USFH facility Infrastructure to support future economic ? development Fulfills master plan goals of Princess Anne ? Commons and provides needed athletic retail services Attract large regional sporting events ? Avoids operating expenses of Sportsplex ? Positive financial impact for the City ? 16