Process Overview
•Virginia’s largest Statewide transportation grant program
•Accept applications biennially
•Applications scored and awarded using metric-based system
•Local match not required; extra points earned if included
•Funding request directly affects score
3
SMART SCALE Metrics
Overview
5%
5%
10%
15%
45%
20%
Economic Development
Safety
Environmental Quality
Accessibility
Congestion
Land Use
❖Resiliency – given consideration however not
factored into score
45%
25%
10%
15%
5%
Congestion
Accessibility
Environmental Quality
Safety
Economic Development
❖Land Use factor as a multiplier on all
other benefits (1+Normalized Score/100)
❖Resiliency remains consideration however
not factored into score
SMART Scale Round 6
5 Weighted Evaluation Measures
(Category A):
SMART Scale Rounds 1-5
6 Weighted Evaluation Measures
(Category A):
SMART SCALE Overview
4
Previous Rounds Take-Aways
•Available Funding Varied; $800M to $1.7B
•VB awarded 15 projects; $138M SMART Scale
•Rounds 1-5: Allowed traffic counts limited to current
year at time of application (no future growth shown)
•Rounds 1 & 2: large high priority projects
•Rounds 3-5: Small projects scored well (~$10M or less)
•Innovative designs scored well all rounds
Round 6 Proposed
•Expected $800M to $1.2B Funds Available (2-year period)
•FY30 & FY31 Funding (Federalized)
•Scoring metrics adjusted (land-use removed)
•Allowed traffic counts changed to look 7 years into the
future to allow expected growth
•Larger projects expected to score better
•Bike and ped projects are no longer preferred
❖ Round 6 guidance still not fully finalized
SMART SCALE Previous Round Award Summary
5
SS Round Total Project Cost
#
Awarded
Projects
SS Award Local Commitment Average Cost of Project
Round 1 $88,000,000 3 $36,000,000 $52,000,000 (59%)$29,333,333
Round 2 $64,077,200 3 $30,000,000 $34,077,200 (53%)$21,359,067
Round 3 $4,100,277 1 $3,600,000 $500,277 (12%)$4,100,277
Round 4 $52,533,647 3 $36,400,000 $16,133,647 (31%)$17,511,216
Round 5 $42,053,639 5 $32,053,639 $10,000,000 (24%)$8,410,728
Total $250,764,763 15 $ 138,053,639 $112,711,124 (45%)$16,717,651
SMART SCALE Previous Round Award Summary
6
Project Name SS
Round Total Project Cost SS Award Local Commitment
Centerville Turnpike Phase III 1 $30,000,000 $6,000,000 $24,000,000 (80%)
Laskin Road Bridge 1 $22,000,000 $10,000,000 $12,000,000 (55%)
Indian River Road Phase VII-A 1 $36,000,000 $20,000,000 $16,000,000 (44%)
Indian River Road Phase VII-B 2 $11,430,000 $5,000,000 $6,430,000 (56%)
Cleveland Street Phase IV 2 $23,647,000 $10,000,000 $13,647,000 (58%)
Laskin Road Phase I-A 2 $29,000,200 $15,000,000 $14,000,200 (48%)
General Booth Blvd/Oceana Blvd Intersection 3 $4,100,277 $3,600,000 $500,277 (12%)
Holland Road Phase I 4 $24,510,485 $16,800,000 $7,710,485 (32%)
Independence Blvd/Edwin Drive Intersection 4 $14,592,026 $9,800,000 $4,792,026 (33%)
Northampton Blvd/Diamond Springs Rd
Intersection 4 $13,431,136 $9,800,000 $3,631,136 (27%)
Clearfield Ave 5 $15,046,279 $10,046,279 $5,000,000 (33%)
General Booth/Dam Neck Intersection 5 $5,269,063 $4,269,063 $1,000,000 (19%)
Independence Blvd/Pleasure House Rd
Intersection 5 $6,402,027 $5,402,027 $1,000,000 (16%)
Indian River/Thompkins Lane 5 $2,669,303 $2,669,303 $- (0%)
Providence Road 5 $12,666,967 $9,666,967 $3,000,000 (24%)
Totals:$250,764,763 $138,053,639 $112,711,124 (45%)
❖ Dam Neck Rd (Princess Anne Rd to Holland Rd)
❖ Dam Neck Rd & Drakesmile Road Intersection
❖ First Colonial Rd (Republic Rd to Old Donation Pkwy)
❖ Independence Blvd & Haygood Rd Intersection
❖ Pacific Ave Turn Lanes (17th St. and 22nd St. Intersections)
❖ Elbow Rd Phase II-D (Salem Rd to Amphitheater Entrance)
❖ Rosemont Rd & Holland Rd Intersection
❖ Laskin Rd Phase II (Oriole Dr. to Saltmeadow Bay Dr.)
❖ VB Trail Phase IV (London Bridge Rd. to Birdneck Rd.)
❖ VB Trail Phase 1
❖ Dam Neck Rd & Drakesmile Road Intersection
❖ First Colonial Rd (Republic Rd to Old Donation Pkwy)
❖ Independence Blvd & Haygood Rd Intersection
❖ Pacific Ave Turn Lanes (17th St. and 22nd St. Intersections)
❖ Laskin Rd Phase II (Oriole Dr. to Saltmeadow Bay Dr.)
❖ VB Trail Phase IV (London Bridge Rd. to Birdneck Rd.)
•4 projects were chosen as recommended candidates:
❖ Dam Neck Rd & Drakesmile Road Intersection
❖ First Colonial Rd (Republic Rd to Old Donation Pkwy)
❖ Independence Blvd & Haygood Rd Intersection
❖ Pacific Ave Turn Lanes (17th St. and 22nd St. Intersections)
❖ Laskin Rd Phase II (Oriole Dr. to Saltmeadow Bay Dr.)
❖ VB Trail Phase IV (London Bridge Rd. to Birdneck Rd.)
7
SMART SCALE Round 6 Candidate Projects
•10 candidate projects identified and evaluated
for SMART Scale Round 6
→Projects were screened using SS Round 6 evaluation
criteria and analyzed for feasibility & priority
•2 additional projects are proposed to submit pre-apps
to determine feasibility for full application:
8
SMART SCALE Round 6 Candidate Projects
SMART SCALE ROUND 6
Exploratory Pre-Applications
•#11 Congested Segment Amongst Un-Funded Projects (2022)
•#12 Congested Intersection Amongst Un-Funded Projects (2022)
•Convert the intersection at Drakesmile Road to a Continuous Green T
(CGT) intersection
•Adds 2 receiving lanes to receive left-turn movement
Benefits:
❖Additional capacity to address congestion
❖Coordinates with active Dam Neck Road/Holland Road
intersection project
❖Stormwater Improvements
❖Improves access to NAS Oceana
❖No site acquisition required
9
Dam Neck Road & Drakesmile Road Intersection
Total Est.
Cost:
$7M
CGT concept image only
10
Dam Neck Road & Drakesmile Road Intersection Existing Conditions Total Est.
Cost:
$7M
11
Dam Neck Road & Drakesmile Road Intersection Proposed Conditions Total Est.
Cost:
$7M
Laurel Lane/ Republic Rd to Old Donation Parkway; Approx. 1 mile
•#10 Congested Segment Amongst Un-Funded Projects (2022)
•Widening First Colonial Rd from 4 lanes to 6 lanes
•Intersection improvements at First Colonial Rd & Wolfsnare Rd
•10’ shared use path on west side
Benefits:
❖Traffic flow improvements & additional capacity to address congestion
❖Improved access to critical medical corridor
❖Signal upgrades (existing span wire signals to mast arm upgrades)
❖Improved access to Hilltop SGA
❖Pedestrian/Bike Improvements
❖Safety benefits
❖Improves transit
12
First Colonial Road
Total Est.
Cost:
$50M
13
Total Est.
Cost:
$50M
First Colonial Road Proposed Conditions
14
Total Est.
Cost:
$50M
First Colonial Road Proposed Conditions
•#1 Congested Intersection Amongst Un-Funded Projects (2022)
•Thru-cut for the eastbound and westbound approaches
•Project optimizes signal timings
•Remove EB and WB thru-movements on Wishart Rd. and Haygood Rd.
Benefits:
❖Innovative intersection to address high congestion
❖Operational signal improvements to improve traffic flow
❖Safety benefits
❖Low Cost
❖No ROW acquisition required
❖Based on 2030 scenarios – overall intersection delay reduced
from 70 seconds to 34 seconds
15
Independence Boulevard & Haygood Road Intersection
Thru -cut concept image only
Total Est.
Cost:
$5M
16
Independence Boulevard & Haygood Road Intersection
Existing Conditions
Total Est.
Cost:
$5M
17
Independence Boulevard & Haygood Road Intersection
Proposed Conditions
Total Est.
Cost:
$5M
•Construct left turn lanes at 22nd Street and at 17th Street
•Pedestrian Median Refuge Areas
•Significant sensitive ROW acquisition required
▪Approx. half of project cost is site acquisition
•Priority zone in VDOT’s Pedestrian Safety Action Plan
•$3M Carbon Reduction Program Funding awarded Feb 2024
Benefits:
❖Safety improvements through dedicated left turn lane
❖Additional capacity to address congestion
❖Improve access to interstate
❖Project will improve traffic flow for Atlantic Park and other
Oceanfront events and venues
18
Pacific Avenue Turn Lanes Total Est.
Cost:
$24M
199
20
Roadways
Fully Funded;
Under Construction
Fully Funded;
Under
Construction
Partially Funded Apply for
SMART SCALE
Round 6
Funding
Laskin Rd Phase III
CIP 100243
Laskin Rd Phase I-A
CIP 100242
Laskin Rd Bridge
CIP 100240
Laskin Rd Phase I-B
CIP 100239
Laskin Rd
Phase II
CIP 100501
Partially Funded;
Funding Plan in Place
With RSTP Funds
Phillip Avenue(I-264)Republic RoadRed Robin RoadOriole DriveLaskin Road Traffic CircleLaskin Rd Corridor Overview
21
Laskin Rd Phase II
Total Est.
Cost:
$20M
Approx. 0.2 miles
•Transitional area between Laskin Rd Phase I-B and 30th/31st Street Roundabout
o Transitions from 6-lane section at Oriole Drive to 4 lanes at roundabout
•Remove service road; convert to shared-use path on Northern side
•Sidewalk improvements
Benefits:
❖Complete the improvements of Laskin Road from First Colonial Road to the resort area
❖Bike and ped improvements
❖No ROW acquisition required
❖Safety benefits through removal of service roads
22
Laskin Rd Phase II
Total Est.
Cost:
$20M
23
VB Trail Phase IV
Total Est.
Cost:
$17M
London Bridge Rd. to Birdneck Rd.; Approx. 2.8 mi.
•14’ wide shared use path
•Eastern Phase connecting to existing Norfolk Ave Trail
•At -grade intersection crossings including HAWK
signal at Oceana Blvd
Benefits:
❖Bike and ped connectivity
❖Pedestrian safety improvements
❖Promote equitable access to an active transportation network
❖Connects underserved communities & development centers
❖No ROW acquisition required
•FY30 & FY31 Local Funds
•Recommendations:
→VDOT advised projects with local match will receive additional points
→Requests for small projects kept to $10M or less; medium projects kept to $20M or less tend to score better
→Full First Colonial improvements viable only with large local commitment; low commitment hinders score
Funding Strategy Recommendations
24
Project Total Project Cost SMART Scale
Request
Appropriated State
& Federal Funds
Local Funds
Commitment
Dam Neck Rd & Drakesmile Rd Intersection $7,000,000 $6,000,000 $-$1,000,000 (15%)
First Colonial Rd $50,000,000 $35,000,000 $-$15,000,000 (30%)
Independence Blvd and Haygood Rd $5,000,000 $4,250,000 $-$750,000 (15%)
Pacific Avenue Turn Lanes $24,000,000 $18,000,000 $3,000,000 $3,000,000 (12.5%)
VB Trail Phase IV $17,000,000 $17,000,000 $-$-
Laskin Road Phase II $20,000,000 $20,000,000 $-$-
Totals:$ 123,000,000 $ 100,250,000 $3,000,000 $19,750,000 (16%)
Next Steps
25
✓VDOT Briefed – January 9th
✓PW Leadership Briefed – January 12th
✓CMOP Briefing – January 19th
✓SMART Portal Opens – March 1st
✓City Council Briefing – March 5th
→Pre-Applications due – April 1st
→City Council Resolution of Support Agenda Item – June/July
→Final Applications due – August 1st
→Project scores and recommended funding scenario released January 2025
Questions?