HomeMy WebLinkAboutI. B. VDOT LASKIN ROAD UPDATE 5.21.24LASKIN ROAD BRIDGE REPLACEMENT
AND WIDENING PROJECT
SCHEDULE UPDATE
Christopher Hall, P.E.
VDOT Hampton Roads District Engineer
May 21, 2024
New Acceleration Incentive for Portion of Project
Virginia Department of Transportation 3
Work to Complete by Nov 2024:
New Milestone Incentive to Expedite High-Impact Sections of Project:
•Laskin Road from Republic Road to
Hilltop North Shopping Center
•First Colonial Road from Laurel Lane
to I-264
•Roadway, Median, Curb and Gutter,
Business Entrances, Sanitary and
Storm Sewer Utility Work, and
Traffic Signals
Final Work After Expedited Portion Complete
•Replacement of Eastbound Bridge
over Linkhorn Bay
•Eastern Section of Project Corridor
(Roadway, Curb & Gutter, Utilities,
Business Entrances, Signal Work)
•Median Lighting for Entirety of
Project Corridor
Virginia Department of Transportation 4
Remaining Work to Complete by Spring 2025:
Final Completion: April 2025
Updated Overall Fixed Contract Completion Date: