HomeMy WebLinkAboutII. A. SMART SCALE UPDATE 6.25.24SMART SCALE Round 6
Final Applications
Katie Shannon, PE | June 25, 2024
SMART SCALE Overview
2
Process Overview
•Virginia’s largest Statewide transportation grant program
•Accept applications biennially
•Applications scored and awarded using metric-based system
•Local match not required; extra points earned if included
•Funding request directly affects score
•Funding typically awarded 6 years out
3
SMART SCALE Metrics
Overview
5%
5%
10%
15%
45%
20%
Economic Development
Safety
Environmental Quality
Accessibility
Congestion
Land Use
Resiliency – given consideration however not
factored into score
45%
25%
10%
15%
5%
Congestion
Accessibility
Environmental Quality
Safety
Economic Development
Land Use factor as a multiplier on all
other benefits (1+Normalized Score/100)
Resiliency remains consideration however
not factored into score
SMART Scale Round 6
5 Weighted Evaluation Measures
(Category A):
SMART Scale Rounds 1-5
6 Weighted Evaluation Measures
(Category A):
SMART SCALE Overview
4
Round 6 Proposed
•Expected $800M to $1.2B Funds Available (2-year period)
•FY30 & FY31 Funding (Federalized)
•Scoring metrics adjusted (land-use removed)
•Larger projects expected to score better
Previous Rounds Take-Aways
•Available Funding Varied; $800M to $1.7B
•VB awarded 15 projects; $138M SMART Scale
•Rounds 1 & 2: large high priority projects
•Rounds 3-5: Small projects scored well (~$10M or less)
•Innovative designs scored well all rounds
SMART SCALE Previous Round Award Summary
5
SS Round Total Project Cost
#
Awarded
Projects
SS Award Local Commitment Average Cost of Project
Round 1 $88,000,000 3 $36,000,000 $52,000,000 (59%)$29,333,333
Round 2 $64,077,200 3 $30,000,000 $34,077,200 (53%)$21,359,067
Round 3 $4,100,277 1 $3,600,000 $500,277 (12%)$4,100,277
Round 4 $52,533,647 3 $36,400,000 $16,133,647 (31%)$17,511,216
Round 5 $42,053,639 5 $32,053,639 $10,000,000 (24%)$8,410,728
Total $250,764,763 15 $ 138,053,639 $112,711,124 (45%)$16,717,651
SMART SCALE Previous Round Award Summary
6
Project Name SS
Round Total Project Cost SS Award Local Commitment
Centerville Turnpike Phase III 1 $30,000,000 $6,000,000 $24,000,000 (80%)
Laskin Road Bridge 1 $22,000,000 $10,000,000 $12,000,000 (55%)
Indian River Road Phase VII-A 1 $36,000,000 $20,000,000 $16,000,000 (44%)
Indian River Road Phase VII-B 2 $11,430,000 $5,000,000 $6,430,000 (56%)
Cleveland Street Phase IV 2 $23,647,000 $10,000,000 $13,647,000 (58%)
Laskin Road Phase I-A 2 $29,000,200 $15,000,000 $14,000,200 (48%)
General Booth Blvd/Oceana Blvd Intersection 3 $4,100,277 $3,600,000 $500,277 (12%)
Holland Road Phase I 4 $24,510,485 $16,800,000 $7,710,485 (32%)
Independence Blvd/Edwin Drive Intersection 4 $14,592,026 $9,800,000 $4,792,026 (33%)
Northampton Blvd/Diamond Springs Rd
Intersection 4 $13,431,136 $9,800,000 $3,631,136 (27%)
Clearfield Ave 5 $15,046,279 $10,046,279 $5,000,000 (33%)
General Booth/Dam Neck Intersection 5 $5,269,063 $4,269,063 $1,000,000 (19%)
Independence Blvd/Pleasure House Rd
Intersection 5 $6,402,027 $5,402,027 $1,000,000 (16%)
Indian River/Thompkins Lane 5 $2,669,303 $2,669,303 $- (0%)
Providence Road 5 $12,666,967 $9,666,967 $3,000,000 (24%)
Totals:$250,764,763 $138,053,639 $112,711,124 (45%)
•6 candidate projects identified and evaluated for
SMART Scale Round 6 pre-applications
Dam Neck Rd & Drakesmile Road Intersection
First Colonial Rd (Republic Rd to Old Donation Pkwy)
Pacific Ave Turn Lanes (17th St. and 22nd St. Intersections)
Laskin Rd Phase II (Oriole Dr. to Saltmeadow Bay Dr.)
VB Trail Phase IV (London Bridge Rd. to Birdneck Rd.)
Dam Neck Rd & Drakesmile Road Intersection
First Colonial Rd (Republic Rd to Old Donation Pkwy)
Pacific Ave Turn Lanes (17th St. and 22nd St. Intersections)
Laskin Rd Phase II (Oriole Dr. to Saltmeadow Bay Dr.)
VB Trail Phase IV (London Bridge Rd. to Birdneck Rd.)
Independence Blvd & Haygood Rd Intersection
Dam Neck Rd & Drakesmile Road Intersection
First Colonial Rd (Republic Rd to Old Donation Pkwy)
Pacific Ave Turn Lanes (17th St. and 22nd St. Intersections)
Laskin Rd Phase II (Oriole Dr. to Saltmeadow Bay Dr.)
VB Trail Phase IV (London Bridge Rd. to Birdneck Rd.)
•5 projects were submitted for pre-applications:
7
SMART SCALE Round 6 Candidate Projects
→Projects were presented to City Council on March 5th, 2024
and analyzed for feasibility & priority
•#11 Congested Segment Amongst Un-Funded Projects (2022)
•#12 Congested Intersection Amongst Un-Funded Projects (2022)
•Convert the intersection at Drakesmile Road to a Continuous Green T
(CGT) intersection
•Adds 2 receiving lanes to receive left-turn movement
Benefits:
Additional capacity to address congestion
Coordinates with active Dam Neck Road/Holland Road
intersection project
Stormwater Improvements
Improves access to NAS Oceana
No site acquisition required 8
Dam Neck Road & Drakesmile Road Intersection Total Est.
Cost:
$10.5M
CGT concept image only
Council
District:
5
9
Dam Neck Road & Drakesmile Road Intersection Existing Conditions Total Est.
Cost:
$10.5M
10
Dam Neck Road & Drakesmile Road Intersection Proposed Conditions Total Est.
Cost:
$10.5M
Laurel Lane/ Republic Rd to Old Donation Parkway; Approx. 1 mile
•#10 Congested Segment Amongst Un-Funded Projects (2022)
•Widening First Colonial Rd from 4 lanes to 6 lanes
•Intersection improvements at First Colonial Rd & Wolfsnare Rd
•10’ shared use path on west side
Benefits:
Traffic flow improvements & additional capacity to address congestion
Improved access to critical medical corridor
Signal upgrades (existing span wire signals to mast arm upgrades)
Improved access to Hilltop SGA
Pedestrian/Bike Improvements
Safety benefits
Improves transit
11
First Colonial Road Total Est.
Cost:
$58.8M
Council
District:
6 , 8
12
First Colonial Road Proposed Conditions Total Est.
Cost:
$58.8M
PROPERTY ACQUISITION
•Construct left turn lanes at 22nd Street and at 17th Street
•Pedestrian Median Refuge Areas
•Significant sensitive ROW acquisition required
Approx. half of project cost is site acquisition
•Priority zone in VDOT’s Pedestrian Safety Action Plan
•$3M Carbon Reduction Program Funding appropriated during
reconciliation of FY25 CIP
Benefits:
Safety improvements through dedicated left turn lane
Additional capacity to address congestion
Improve access to interstate
Project will improve traffic flow for Atlantic Park and other
Oceanfront events and venues 13
Pacific Avenue Turn Lanes Total Est.
Cost:
$29.9M
Council
District:
5, 6
149
Pacific Avenue Turn Lanes Proposed Conditions
PROPERTY ACQUISITION
Total Est.
Cost:
$29.9M
159
Pacific Avenue Turn Lanes Proposed Conditions
PROPERTY ACQUISITION
Total Est.
Cost:
$29.9M
16
Roadways
Fully Funded;
Under Construction
Fully Funded;
Under
Construction
Partially Funded;
Funding Plan in
Place With RSTP
Funds
Apply for
SMART SCALE
Round 6
Funding
Laskin Rd Phase III
CIP 100243
Laskin Rd Phase I-A
CIP 100242
Laskin Rd Bridge
CIP 100240
Laskin Rd Phase I-B
CIP 100239
Laskin Rd
Phase II
CIP 100501
Partially Funded;
Funding Plan in Place
With RSTP Funds
Phillip Avenue(I-264)Republic RoadRed Robin RoadOriole DriveLaskin Road Traffic CircleLaskin Rd Corridor Overview
17
Laskin Rd Phase II
Total Est.
Cost:
$19.9M
Approx. 0.2 miles
•Transitional area between Laskin Rd Phase I-B and 30th/31st Street Roundabout
o Transitions to 4 lanes from Oriole Drive at roundabout
•Remove service road; convert to shared-use path on Northern side
•Sidewalk improvements
Benefits:
Complete the improvements of Laskin Road from First Colonial Road to the resort area
Bike and ped improvements
No ROW acquisition required
Safety benefits through removal of service roads
Council
District:
6
18
Laskin Rd Phase II
Total Est.
Cost:
$19.9M
19
VB Trail Phase IV
Total Est.
Cost:
$24.7M
London Bridge Rd. to Birdneck Rd.; Approx. 2.8 mi.
•14’ wide shared use path
•Eastern Phase connecting to existing Norfolk Ave Trail
•At -grade intersection crossings including HAWK
signal at Oceana Blvd
Benefits:
Bike and ped connectivity
Pedestrian safety improvements
Promote equitable access to an active transportation network
Connects underserved communities & development centers
No ROW acquisition required
Council
District:
5 , 6
20
VB Trail Phase IV
Total Est.
Cost:
$24.7M
•FY30 & FY31 Local Funds (outer year funding)
•Recommendations:
→VDOT advised projects with local match will receive additional points
→Requests for small projects kept to $10M or less; medium projects kept to around $20M tend to score better
→Full First Colonial improvements viable only with large local commitment; low commitment hinders score
→Costs maintain assumptions for VDOT Oversight Costs until directly received from VDOT in July
Funding Strategy Recommendations
21
Project Total Project Cost SMART Scale
Request
Appropriated State
& Federal Funds
Local Funds
Commitment
Dam Neck Rd & Drakesmile Rd Intersection $10,500,000 $9,500,000 $-$1,000,000 (9.1%)
First Colonial Rd $58,800,000 $43,800,000 $-$15,000,000 (25.5%)
Pacific Avenue Turn Lanes $29,900,000 $21,900,000 $3,000,000 (10%)$5,000,000 (16.7%)
VB Trail Phase IV $24,700,000 $24,700,000 $-$-
Laskin Road Phase II $19,900,000 $19,900,000 $-$-
Totals:$ 143,800,000 $ 119,800,000 $3,000,000 $21,000,000 (14.6%)
Next Steps
22
CMOP Briefing – January 19th
SMART Portal Opened for Pre-Applications – March 1st
City Council Pre-Application Briefing – March 5th
Pre-Applications due – April 1st
SMART Portal Opened for Final Applications – June 3rd
City Council Final Application Briefing – June 25th
→Council Resolution of Support Agenda Item – July 2nd
→Final Applications due – August 1st
→Project scores and recommended funding scenario released January 2025
Questions?