HomeMy WebLinkAboutI. B. VIOLET BANK TRAIL UPDATE 11.19.2024VIOLET BANK TRAIL
Pedestrian Facility ADA Requirements & Trail Options
November 19, 2024
LJ Hansen
Director of Public Works
Why are We Here?
•Two Citizen Information Meetings revealed divided opinions on the trail:
some favored the recommended design, while others support a paved or alternative
surface. Difference also as it related to the width or need for trail at all.
•Main concerns about the project include tree impacts and environmental
preservation.
•Federal, State and City Standards require an ADA-compliant pedestrian facility if a
project is undertaken.
•In summer of 2024, City Council requested an evaluation of ADA-compliant
alternative trail surfaces.
•A summary of costs, funding, and project implications for different trail options will
be presented.
2
Location Map
Bellamy ManorStratford Chase
Bellamy Woods
Bellamy Manor Estates
Indian Lakes
3
Indian Lakes Elementary School
Project Details
Description and Scope
•The connection from Violet Bank Drive to Selwood Drive is currently an unpaved footpath.
•Original Project Scope: 10-ft shared-use path with drainage ditch improvements, street
crossings, sidewalk, and ADA ramps – Drainage is no longer in the current scope
Purpose and Need
•Improve pedestrian safety and accessibility to Providence Elementary, Kempsville Middle
and High Schools, the Kempsville Library, and the Recreation Center with an ADA-compliant
facility.
Funding and Current Status
•TAP Funding: $318,848, CIP Funding: $1.6 million
•8-ft wide asphalt sidewalk design underway ~ 90% Complete
•Advertise for Construction: Late 2025 or early 2026
•Ditch maintenance originally scheduled for 2029 4
Stormwater Ditch Maintenance
•Existing ditch is heavily overgrown with trees and
debris. Inadequate flow results in flooding issues
for community
•Some utilities are in ditch boundaries
•Currently scoping the design work – anticipating
coordination of Public Information Meetings
•Award of workorder for design in early 2025
•Expected to complete design work late 2025 or
early 2026
•Construction to be awarded following completion
of the design services (Expect late 2026)5
Pedestrian Facility Requirements & Standards
Agency Standard Surface Minimum Width
Minimum
Shoulder
Width
US Gov ADA Stable, Firm, and
Slip-resistant
3 ft
5 ft x 5 ft passing
area every 200 ft)
N/A
City Sidewalk Concrete, or pavers 5 ft 1 ft
City Wide Sidewalk Asphalt, concrete, or
pavers in urbanized areas 8 ft 1 ft
City Shared-Use Path Asphalt or concrete 10 ft 2 ft,
3 ft clear
VDOT Sidewalk Stable, Firm, and
Slip-resistant
5 ft, 4ft clear
(5 ft x 5 ft passing
area every 200 ft)
1 ft
VDOT Shared-Use Path
Asphalt or Concrete are
Preferred over Crushed
Aggregate, Sand, Clay, or
Stabilized Earth
10 ft preferred
8 ft allowed 2 ft, 3 ft clear
Applies to All
•Max. Grade: 1:20 (5%)
•Max. Cross Slope: 1:48 (2%)
•Max. Vertical Change: ¼-inch, or
between ¼-inch to ½-inch if beveled
•Min. Vertical Clearance: 80 inches,
96 inches for Shared-Use Path
6
Trail Options and Considerations
7
ADA -Compliant
Pedestrian Options
Surface
Material
Tree Clearing
Width for Access
and Construction
Ditch
Maintenance Will
Adversely Impact
Trail
Temporary
Construction
Easements
Required 14
Parcels (Max)
Condemnation
Ordinance
Required For
Temporary
Easements
TAP Grant Funding Implications
*No-Build
Leave As-Is
(Not required to be
ADA-compliant)
Dirt N/A Yes No No
•Return TAP reimbursed expenses.
•50-point deduction on future TAP
grant applications for the next 5
years.
3 ft Wide
(Min. ADA Requirements)
Various
(excludes Hot
Mix Asphalt)
8 ft
(Less than 72
trees to be
removed)
Yes Yes Yes
(12 parcels)
•Return TAP reimbursed expenses.
•50-point deduction on future TAP
grant applications for the next 5
years.
•Design variance approval required
by City.
5 ft Wide
Various
(excludes Hot
Mix Asphalt)
8 ft to 10 ft
(Approx. 72 trees
to be removed)
Yes Yes Yes
(13 parcels)
•No impact to TAP funding.
•Project scope change approval
required by VDOT.
•Must maintain VDOT project
schedule. Construction
advertisement 8/2025.
8 ft Wide Hot Mix Asphalt
10 ft to 16 ft
(Approx. 72 trees
to be removed)
No, but spot
repairs may
be required
Yes Yes
(14 parcels)
•No impact to TAP funding.
•Must maintain VDOT project
schedule. Construction
advertisement 8/2025.
* Wait for completion of ditch maintenance to construct 3-ft, 5-ft, or 8-ft sidewalks with City funds.
No Build Option
Near Selwood Drive Near Shenvalee Drive Near Flobert Drive 8
Surface Material Type Analysis (5-ft Width)
9
Surface
Initial Installation
Cost (5-ft wide,
1750 SY)
Total Maintenance
Cost Over 25 Years
(5-ft Wide)
Installation Cost +
Maintenance Cost
(5-ft Wide)
Rank Cost Difference
(5-ft Wide)
No. 6 -Hot Mix Asphalt $100,000.00 $89,375.00 $189,375.00 1 $-
No. 3 –Color Chip Seal $115,625.00 $96,875.00 $212,500.00 2 $23,125.00
No. 4 -Hot Mix Asphalt +
Color Chip Seal $117,500.00 $131,875.00 $249,375.00 3 $60,000.00
No. 1 -Stone Dust $82,500.00 $237,500.00 $320,000.00 4 $130,625.00
No. 2 -Organic Lock
Stabilized Stone $150,625.00 $379,687.50 $530,312.50 5 $340,937.50
No. 5 -Flexi-Pave $192,500.00 $503,125.00 $695,625.00 6 $506,250.00
Notes: 1 -Material costs only (NOT PROJECT COSTS)
2 -Does not include inflation
Project Options Summary
1.Leave trail As-is
•Return TAP Funding to the State and receive a 50-point deduction on future TAP applications
•City-funded trail can be constructed after completion of 2029 ditch maintenance
2.Construct 3-ft Option
•Return TAP Funding to the State and receive a 50-point deduction on future TAP applications
•Requires redesign which impacts budget and schedule
•Design variance required by City
•City-funded trail can be constructed
3.Construct 5-ft Option
•Requires redesign which impacts budget and schedule
•Project scope change approval required by VDOT
4.8 ft Wide Asphalt Sidewalk – Continue Design
10
Project Options Summary
11
Options Leave Trail As-Is 3-ft wide 5-ft wide 8-ft wide
ADA-Compliant
Redesign Required
Return TAP funds (50 pt
deduct on future apps)
VDOT Schedule Impacts
2029 Ditch Maintenance
will impact the trail
Tree Impacts
Acquisition Required
Trail Functionality
12
Project Scope after reviewing all options and in keeping with original scoping
•Trail width 8-ft wide
•Trail surface material: No. 6 Hot Mix Asphalt
Rationale
•Design is almost complete (90%)
•Completely ADA Compliant
•Satisfies TAP Requirements
•Highest Functionality – serves all users with ample room for passing
•8ft trail requires the removal of same number of trees as 5ft trail (72 trees)
•Lowest Long Term Maintenance Costs – Asphalt is durable & does not require
extensive yearly maintenance
Selected Design
13
An Ordinance to authorize the acquisition of permanent and temporary
easements either by agreement or condemnation
•Public Hearing December 3, 2024
•Adoption of Ordinance December 10, 2024
An Ordinance to amend FY25 CIP 100558 Violet Bank Trail to add Site
Acquisition, Private Utility Adjustment,and Contingency phases
•Adoption of Ordinance December 10, 2024
Next Steps – Unless Directed Otherwise
THANK YOU
Discussion
14
15
•Surface material type is a separate issue from the path width
•City can make alternative surface materials ADA-compliant by committing to
regular maintenance
•Case could be made to try alternative surface material initially to confirm
performance and maintenance costs
•If necessary, the surface could always be paved at a later date
Surface Material Type Analysis
16
3-ft and 5-ft Option:Surface No. 1 – Stone Dust
•ADA -Compliant – If maintained
•4-inch Stone Dust over 6-inch Dense Graded
Crushed Stone
•Fine textured gravel,less stable surface
•Will support vehicles (maintenance
increases proportionally with vehicle use)
•$82,500 installation cost (5-ft option)
•5-year life cycle: Replace 4-inch stone dust
o $35,000 / every 5 years (5-ft option)
•At least yearly spot maintenance to
replenish high-use areas.
o $2,500 / year (5-ft option)Treatment 1: Stone Dust.Champlain Canalway Trail, New York
17
3-ft and 5-ft Option: Surface No. 2 – Organic Lock Stabilized Stone
•ADA-Compliant – If maintained
•4-inch organic lock stabilized stone over 6-inch dense
graded crushed stone
•Natural soil appearance,many color options, hard
surface when dry, slightly deformable when wet.
•Occasional light vehicles such as pickup (except
during saturated conditions during/after rain events)
•$150,625 installation cost (5-ft option)
•Estimated 10-year life cycle: Replace 4-inch organic
lock stabilized stone
o $101,878 / every 10 years (5-ft option)
•Yearly spot maintenance. Most defects can be repaired
with hand tools
o $5,000 / year (5-ft Option)
Treatment 2: Organic Lock Stabilized Stone Surface, Delaware
Water Gap National Recreational Area (Client: National Park
Service)
18
3-ft and 5-ft OptionSurface No. 3 – Color Chip Seal
•ADA-Compliant – If maintained
•Double layer of color chip seal over 8-inch
dense graded crushed stone
•Coarse aggregate texture with stone color
options available to match the surroundings
•Light vehicle use (car or pickup)
•$115,625 installation cost (5-ft option)
•10 to 15-year life cycle: Replace double-
layer chip seal
o $38,750 / every 10 years (5-ft option)
•Very low annual maintenanceTreatment 3 Color Chip Seal – Blacktop Northwest LLC – Hubbard,
Oregon
19
3-ft and 5-ft OptionSurface No. 4 – Hot Asphalt Mix + Color Chip Seal
•ADA Compliant
•2-inch hot mix asphalt + single layer of color chip
seal over 6-inch dense graded crushed stone
•Coarse aggregate texture with stone color options
available to match the surroundings
•Light vehicle use (car or light truck)
•$117,500 installation cost (5-ft option)
•25-year life cycle hot mix asphalt: Replace 2-inch
hot mix asphalt surface
•$78,750 / every 25 years (5-ft option)
•Asphalt patching (5% of the area) and chip seal
replacement every 10 years
o $21,250 / every 10 years (5-ft option)Treatment 4: Hot Mix Asphalt + Color Chip Seal,
Stellar Striping and Seal Coating, Austin, Texas
20
3-ft and 5-ft Option Surface No. 5 – Flexi-Pave
•ADA -Compliant
•2-inch flexi-pave over 4-inch open-graded stone
•Natural, organic look with a textured finish,
multiple color options
•Light vehicle use (car or light truck)
•$192,500 installation cost (5-ft option)
•10 to 15-year life cycle: Replace 2-inch flexi-
pave surface
o $182,500 / every 10 years (5-ft option)
•Frequent removal of debris from the surface
needed for maintenance
o $1,875 / year (5-ft option)
Treatment 5: Flexi-Pave, Cypress Avenue & 23rd Street
(Client: City of Virginia Beach)
21
8-ft Option (Approved Option Under Design) Surface No. 6 – Hot Mix Asphalt
•ADA -Compliant
•2-inch hot mix asphalt over 6-inch dense
graded crushed stone
•Black top smooth asphalt
•Light vehicle use (car or light truck)
•$100,000 installation cost (5-ft option)
•20 to 25-year life cycle: Replace 2-inch hot mix
asphalt surface
•$70,625 / every 25 years (5-ft option)
•Asphalt patching (5% of area) and crack seal
every 10 years
o $7,500 / every 10 years (5-ft option)Treatment 6 Hot Mix Asphalt. Marshview Park,
Virginia Beach
22
•Project Scope requires City Council decision
•Trail width option: Leave Trail As-Is, 3-ft, 5-ft, or 8-ft wide
•Trail surface material: No. 1 Stone Dust, No. 2 Organic Lock Stabilized Stone, No. 3 Color
Chip Seal,No. 4 Hot Mix Asphalt + Color Chip Seal, No.5 Flexi-Pave, No. 6 Hot Mix
Asphalt
•Items that need City Council approval
•An Ordinance to authorize the acquisition of permanent and temporary easements
either by agreement or condemnation
•Public Hearing November 26, 2024
•Adoption of Ordinance December 3, 2024
•An Ordinance to amend FY25 CIP 100558 Violet Bank Trail to add Site Acquisition,
Private Utility Adjustment,and Contingency phases
•Public Hearing November 26, 2024
•Adoption of Ordinance December 3, 2024
Direction On a Path Forward
23
•Resident filed a complaint with DOJ
•Updated DOJ on status
•DOJ agrees with legal assessment of ADA requirements
•DOJ advising resident final decision not made yet and the resident can attend
public sessions to provide input.
Complaint to the Department of Justice (DOJ)