HomeMy WebLinkAboutIII. B. Shore Drive Phase 3 Project 1.14.2025Shore Drive Corridor Improvements Phase III
Construction Funding
City Council Briefing
LJ Hansen, P.E. | January 14, 2025
Purpose of Project
•The purpose of this project is to improve
safety for motorists, pedestrians, and
bicyclists while providing the corridor
with aesthetic elements such as
landscaping, hardscape, and lighting.
•Does not increase roadway capacity -no
new lanes of travel.
2
Today's Presentation – Cost Increases
•October 10, 2024: Project advertised for construction bids
•November 12, 2024: Bid Opening – (Price Holds for 90 Days – Feb
11th)
•Two bids were received above the Engineer's Estimate:
•Engineer's Estimate (Combined PW, PU & HRSD): $48.2M
•Excluding Contingencies
•Bidder #1:$68.7M - Low Bidder – Deemed to be a qualified bid
•Bidder #2: $93.4M
•Lowest Bidder Exceeded the Engineer's Estimate 3
Project History
•2008: First appeared in the FY 2007-2008 CIP
•2010 & 2023: Funding transferred from Shore Drive Phase IV to this project
•2012-2014: Design suspended during flood study of Cape Henry Canal
•2014-2016: Stormwater modeling and design
•2016-Present:
•Design revised in coordination with the Eastern Shore Drive Drainage
Flood Protection Program projects to meet new SW design
•Private Utility relocations
•Real Estate acquisitions
4
Current Project Scope
•1.2 miles of new road with curb and gutter from Vista Circle to Beech Street
•Raised medians with landscaping/hardscape materials
•5-foot-wide on-street bike lane
•5-foot-wide concrete sidewalk, except between Lesner Bridge and Jade Street
•10-foot-wide shared-use path from the Lesner Bridge to Jade Street to
provide a connection to the Cape Henry Trail
•New drainage pipes and structures
•Property entrances consolidated and oriented to the side streets
where practical
•Raised roadway profile to address areas of known flooding 5
Project Scope
•Overhead utilities will be relocated and placed underground at the intersections and
mid-block crossings to improve visibility as well as aesthetics
•New streetlights and upgraded traffic signals with mast arm signal equipment
•Stamped asphalt crosswalks and improved signage
•Landscaping between the curb and the sidewalks
Project Funding Deficit
Engineer’s Estimate: $48.2M
Bidder #1: $68.7M*
Bidder #2: $93.4M*
DPW Roadways Deficit: $21.8M (includes 10% contingency)
DPU Betterments Deficit: $4.2M
HRSD Betterments Deficit: $1.6M
Total Deficit: $26.0M – (Does not include HRSD Portion)
*Bid prices expire February 10, 2025
7
Large Cost Drivers
•Signals & Lighting: $6.7M
•Contractor could only obtain one sub-quote (from Richmond)
•Pavement & Patching Items: $2.0M
•Concrete Pipe: $1.5M
•Ductile Iron Water Main: $1.0M
•Ductile Iron Sewer Force Main: $600K
•Contaminated groundwater/soil: $800K
•Landscaping: $500K
•Maintenance of Traffic: $7.5M
•Contractor attributes to night work, traffic control 8
Contractor Challenges
•Constructing the project on an active roadway with limited ROW
•Maintaining four lanes of traffic, pedestrian access, and drainage
•Daytime and Seasonal work hour constraints
•Night Work: two full crews, daily lane shifts/traffic control,concrete &
asphalt difficult to obtain
•Detour ~18 miles
•High water table complicates excavations, requires dewatering
•Utilities crossing multiple live traffic lanes
9
Market Challenges
•Recent bid tabulations are not directly comparable due to night work
•Saturated Local Construction market:
•HRBT expansion, CBBT expansion, CV Off-Shore Wind,State and Local
projects competing for resources
•Received only two bids
•Inflation, interest rates,and labor shortages (American Rescue Plan
2021, Infrastructure Investment & Jobs Act 2021, CHIPS and Science Act
2022, Inflation Reduction Act 2022)
•Cost of Highway Materials National Inflation (2021 Q1 – 2024 Q1) 91%*
*National Highway Construction Cost Index 10
Potential Savings
Discussion with Low Bidder
•$2M if daytime lane closures are permitted for 8+ hours
(no reduction in contract time offered)
•$1.2M if Ductile Iron Sewer Force Main changed to directionally drilled
High-density polyethylene (HDPE) pipe
•Would require design revisions: ~$50K, up to 8 weeks
•$1.7M in reduced unit prices for select Signals & Lighting items
•$300K if City provides a laydown area for materials, trailers, equipment
11
Alternatives for City Council to Consider
1.Do nothing, cancel the project, reallocate funds to other projects
+ Positive impact to other CIP projects
- Project strongly supported by Advisory Groups for 20+ yr
- Impacts Eastern Shore Drive Drainage Improvements projects
2.Defer project until market conditions improve and/or
additional funding is appropriated
+ No impact on CIPs
- Delay will not meet expectations of residents and stakeholders
- Costs likely to increase with time
12
Alternatives for City Council to Consider
3.Modify Scope and Rebid the project
+ Can provide longer bid window to attract contractors
+ Potential to include cost-saving design revisions
- Delays project, bids could increase, could receive no bids
4.Fund Deficit from PW Roadway and PU CIP projects or another Council Funding Source
+ Allows project to advance
- Impacts donor project delivery schedule
- Requires Ordinance – Feb 4th
13
Potential Donor Projects
Potential Project Local Funds Available
Indian River Road VII-A $ 36,776,661
Rosemont Road Phase V $ 14,329,473
Centerville Turnpike III $ 41,982,274
Cleveland Street IV $ 13,377,949
Discussion
Questions?
Project Funding Deficit Details
16