2
Purpose
•Provide the history and background of
the Atlantic Avenue Improvement
Project
•Review status of the Atlantic Avenue
Design Build Project
•Design Concepts
•Schedule and Phasing
•Budget
•Seek direction on the future of the
project
3
Atlantic Avenue –
The Beach Main Street
•Atlantic Avenue is a featured, iconic street
in the Resort Area and along the East Coast
•Rich with tradition, history, and nostalgia
•Provides the full resort experience with
places to shop, stay, eat, and be
entertained
•It’s a host to thousands on foot, wheels or
vehicles as well as parade’s, races, and
cultural events annually
•Its where trends first emerge
Seasonal ‘Live On Atlantic!’ Performances
2020 Small Cell
Tower Advent
2018 Scooter
Invasion
4
History
•Atlantic Avenue between 2nd and
40th Streets has evolved over time
•1982 – Refresh Plan
•1985 - Revitalization Project
•1989 - 1996 Phased Atlantic Ave
Streetscape Improvements
Constructed – still in place today
Atlantic Avenue Circa 1932
Atlantic Avenue Circa 1979
5
Existing Conditions
6
Existing Conditions2
7
Background
•2017 – Grassroots Advocacy for revitalization (Atlantic Avenue Association Formed)
•2018 – Activate Atlantic Avenue Visioning Workshops
•2020 – RASAP Update & Atlantic Ave CIP Adopted
•2021 – The Ave Demonstration Project
•2023 – RAMP Adoption & Streetscape Design Guidelines
•2024 – Progressive Design-Build Contract Awarded ‘The Ave’ Demonstration Project 2021-2022
8
The Resort Area Mobility Plan (RAMP)
The scope for Atlantic Avenue rehabilitation was developed and refined during the RAMP process based on substantial community input and data collection:
When asked how the space
along Atlantic Avenue should
be prioritized, (1 being the
greatest priority and 5 being
the least), survey participants
place a premium on space
for pedestrians and bicyclists
4.17
4.17
4.04
3.61
2.74
1.7
SPACE FOR CARS
CORRALS FOR ELECTRIC SCOOTERS
SPACE FOR ON-STREET PARKING
SPACE FOR TRANSIT VEHICLES
SPACE FOR BICYCLES
SPACE FOR PEDESTRIANS
9
The Resort Area Mobility Plan (RAMP)2
The decision to recommend the elimination of on-street parking for
increased pedestrian space and streetscape was carefully analyzed and
considered in the recommendation:
•Pedestrian counts collected in July 2021,
recorded thousands on foot on Atlantic Avenue
•Positive feedback was received on The AVE
•Negative feedback was received by first
responders concerning the on-street parking
•Seasonal parking data showed only 40% of the
blocks experienced consistent use
•55% of respondents indicated they weren’t
aware of the on-street parking or rarely used it
Temporary Off-Season On-Street Parking
has been offered along Atlantic Ave since
2018 between October and April
10
Atlantic Avenue Design Concept
17th to 25th Street - Representative Segment
11
Flyover Video
12
Atlantic Avenue Design-Build Project Team
OWNER’S REPRESENTATIVE
ARCHER WESTERN
(PRIME CONTRACTOR)
RINKER DESIGN ASSOC.
(PRIME DESIGNER)
13
Atlantic Avenue Phasing & Budget
As conceived in the RAMP, the Atlantic Avenue CIP is divided into three
distinct segments between 5th and 40th streets
Project Number/Name District Year of
Origin Source ATD FY26 FY27 Total BTC
100300: Atlantic Ave
Street Improvements 5, 6 2020
Tourism
Investment
Fund (TIP)
33,900,000 7,900,000 6,300,000 48,100,000 60,900,000
14
Atlantic Avenue Schedule
•The first segment
between 17th and 24th is
fully funded with the ATD
and FY 26 programmed
funding
•On track for construction
in the Fall of 2025
•More value engineering
and funding is needed on
future north and south
segments
Project Schedule Date
30% Design NTP May 1, 2024
Over-the-Shoulder Reviews (OTSR)June 2024 – August 2024
30% Design Plan Submission October 1, 2024
Design Concurrence/Approval November 2024
100% Design NTP January 2025
GMP Approval - Segment 2 Summer of 2025
Meetings and Outreach January 30, 2025 &
Summer 2025
Construction - Segment 2 Fall 2025 - Spring 2026
Construction (Segments 1 & 3)*Fall 2026 - Spring 2027*
Fall 2027 - Spring 2028*
*Future segments subject to appropriation
Atlantic Avenue Phasing & Budget2
•Full rehabilitation between 17th and 24th can occur within funding through FY26
•Likely also be able to repave and mark the roadway within curb line between 24th and 40th within funding through FY27
15
Full rehabilitation Fall ’25 – Spring ‘26 Repaving and marking within curb line
Fall ’26 – Spring ‘27
Atlantic Avenue Next Steps
•A decision is needed to proceed at this time in order to make the Fall 2025 construction start
•A public meeting is scheduled from 6-8 p.m. on Thursday, Jan. 30, 2025, at the Virginia Beach Convention Center, 1000 19th Street to:
•View design concepts designs and details
•Learn about project
•Collect valuable feedback to help shape the future of Atlantic Avenue
•VirginiaBeach.gov/AtlanticAvenue
16
Alternatives for Consideration
17
A.Proceed with first segments within
existing and programmed funding
as currently planned
B.Seek additional value engineering options
C.Pause further action until the conclusion of
the upcoming CIP retreat
D.Other as directed