HomeMy WebLinkAboutII. A. 8. Roadways CIP 4.22.2025PROPOSED FY 2025-26 to FY 2030-31
ROADWAYSCAPITAL IMPROVEMENT PROGRAM
David Jarman, PE
Public Works
April 22, 2025
Roadways Overview
•FY 2025-26 Proposed CIP –57 projects:
•$991.5 Programmed Funding:
•Appropriations to Date: $649.1 M
•Programmed Years 1-6: $342.4 M
•Funding Sources:
•General Fund
•Federal Funding
•State Funding
•Speed Enforcement
•Major Projects Fund
2
Sandbridge Road--Nimmo Phase VII-A under
construction (looking east)
Roadways Total Funding
54%
23%
23% City Funding Years 1-6: $185.5 M (54%)
State Funding Years 1-6: $79.0 M (23%)
Federal Funding Years 1-6: $78.0 M (23%)
Total Funding in Years 1-6: $342.4 M
Total ATD Funding: $649.1 M
Federal
City
State
Total
Roadways
Funding
Years 1-6
Total Roadways Programmed Costs: $991.5 M
3
Roadways Local Funding Overview
33%
27%
16%
18%
6%
Congestion Relief & Capacity Impr. - $60.5 M (33%)
Safety Improvements - $51.1 M (27%)
Special - $29.8 M (16%)
Maintenance - $32.9 M (9%)
Bridge - $11.2 M (3%)
→30 Projects/Programs
→14 Projects/Programs
→8 Projects/Programs
→3 Programs
→2 Projects
City
Roadways
Funding
Years 1-6
Special
Maint.
Bridge
Congestion
&
Capacity
Safety
Total City Funding in Years 1-6: $185.5 M
57 Total Projects/Programs 4
Projects with No Change (1/4)
Project Council
District
Appropriations
to Date FY26 Budget FY27-31
Budget Total Balance to
Complete
Atlantic Avenue Pedestrian Improvements: 100633 6 1,772,867 --1,772,867 1,269,274
Centerville Turnpike Phase II: 100057*7 71,998,614 -788,603 72,787,217 4,285,181
Clearfield Avenue: 100650*4 -900,000 14,146,279 15,046,279 -
Dam Neck Road/Holland Road Intersection Imp: 100537**2,10 3,296,658 --3,296,658 -
Elbow Road Extended Phase II-B: 100529*2 68,050,361 --68,050,361 -
Elbow Road Extended Phase II-C: 100159*2 33,171,325 --33,171,325 -
Elbow Road Phase II-D: 100160*2 3,500,000 5,000,000 -8,500,000 45,220,928
First Colonial Rd/Va. Beach Blvd. Intersection Imp: 100183*6 34,765,516 --34,765,516 -
General Booth Blvd/Camp Pendleton Inter. Imp: 100192***5,6 3,739,500 --3,739,500 -
General Booth Blvd/Dam Neck Road Inter. Imp: 100648*5 -600,000 4,669,063 5,269,063 -
General Booth Blvd/Oceana Blvd Inter. Imp: 100542*5 4,530,770 --4,530,770 -
* Project partially State/Federal Funded **Project 100% State/Federal Funded ***Project Also Includes Non-Programmed Funds 5
Projects with No Change (2/4)
Project Council
District
Appropriations
to Date FY26 Budget FY27-31
Budget Total Balance to
Complete
Greenwich Rd Crossover/Cleveland Str Imp: 100199*4 16,199,414 289,747 -16,489,161 -
Holland Road Phase I: 100564*3,10 546,876 1,495,613 22,125,068 24,167,557 4,095,294
Holland Road Phase II: 100565*3,10 500,000 -2,213,992 2,713,992 -
I-264/Independence Interchange Improvements: 100211***3,4 500,000 --500,000 221,250,000
Independence Blvd/Edwin Drive Intersection: 100482*3 -5,000,000 10,838,863 15,838,863 3,746,099
Independence Blvd/Pleasure House Rd Intersection: 100647*9 32,718 750,000 6,821,576 7,604,294 -
Indian River Rd / Thompkins Lane Intersection: 100646**1,7 298,126 350,000 2,319,303 2,967,429 -
Indian River Road Bridge (Speed Fentress): 100659 2 1,000,000 --1,000,000 103,491,414
Landstown Road Phase I: 100235 2 4,214,276 --4,214,276 24,326,360
Laskin Road Phase I-B: 100239*6 7,278,981 -18,944,279 26,223,260 33,213,779
Laskin Road Phase II: 100501*6 783,111 --783,111 20,468,296
* Project partially State/Federal Funded **Project 100% State/Federal Funded ***Project Also Includes Non-Programmed Funds 6
Projects with No Change (3/4)
Project Council
District
Appropriations
to Date FY26 Budget FY27-31
Budget Total Balance to
Complete
Laskin Road Phase III: 100243**6 --30,316,014 30,316,014 18,337,330
Leading Pedestrian Interval Intersection Improvements: 100683 Citywide 35,000 100,000 846,750 981,750 -
Nimmo Parkway Phase VII-B: 100278*2,5 19,962,349 12,250,000 21,759,151 53,971,500 20,744,835
N. Great Neck Road Bridge Rehabilitation: 100672 8 -11,232,666 -11,232,666 1,127,500
N. Great Neck/London Bridge/VB Blvd Inter. Imp: 100546**3,6,8 3,021,829 -400,000 3,421,829 -
Northampton Blvd/Diamond Springs Road Intersec: 100568*4,9 710,029 5,000,000 13,843,911 14,553,940 -
Pacific Avenue Turn Lanes: 100673*5,6 2,000,000 1,000,000 1,000,000 3,000,000 29,864,643
Parliament Drive Sidewalk Phase I: 100555*1 3,674,525 --3,674,525 -
Parliament Drive Sidewalk Phase II: 100301*1 4,332,907 --4,332,907 -
Pleasure House Road Phase I: 100524 9 117,139 --117,139 16,620,854
Pleasure House Road Phase II: 100306 9 3,266,289 --3,266,289 23,008,646
* Project partially State/Federal Funded **Project 100% State/Federal Funded ***Project Also Includes Non-Programmed Funds 7
Projects with No Change (4/4)
Project Council
District
Appropriations
to Date FY26 Budget FY27-31
Budget Total Balance to
Complete
Providence Road: 100649*1,3 -1,500,000 12,666,967 12,666,967 -
Sandbridge Road Sidewalk: 100556*2,5 1,360,750 --1,360,750 -
Shore Drive Corridor Improvements Phase III: 100382*8 72,165,498 --72,165,498 -
Shore Drive Corridor Improvements Phase IV: 100383*9 13,632,181 3,500,000 7,500,000 21,132,181 71,366,422
Upton Dr Extended/Dam Neck Station Imp: 100429 5 1,300,000 --1,300,000 -
Woodstock Road Sidewalk: 100682 1 150,000 --150,000 2,850,125
* Project partially State/Federal Funded **Project 100% State/Federal Funded ***Project Also Includes Non-Programmed Funds
8
Programs with No Change
Project Council
District
Appropriations
to Date FY26 FY27 FY28 FY29 FY30 FY31 Total
Bus Stop Infrastructure & Accessibility
Improvements*: 100050 Citywide 1,917,126 -250,000 250,000 250,000 250,000 250,000 3,167,126
City Wide Street Lighting Improvements III:
100502 Citywide 350,000 70,000 70,000 70,000 70,000 70,000 70,000 770,000
Construction Engineering and Inspections
(CEI) Program: 100634 Citywide 10,500,000 3,500,000 3,500,000 3,500,000 3,500,000 3,500,000 3,500,000 31,500,000
Major Bridge Rehabilitation II: 100268 Citywide 22,040,284 1,460,000 1,460,000 1,460,000 1,460,000 1,460,000 1,460,000 30,800,284
Rural Road Improvements II: 100347 Citywide 2,254,424 250,000 250,000 250,000 250,000 250,000 250,000 3,754,424
Rural Road Recurring Flooding, SLR, &
Resiliency: 100348 Citywide 500,000 500,000 500,000 500,000 500,000 500,000 500,000 3,500,000
Street Reconstruction II*: 100401 Citywide 47,322,635 3,450,000 2,150,000 2,150,000 2,150,000 2,150,000 2,150,000 61,522,635
Traffic Calming: 100422 Citywide 1,150,000 250,000 2,150,000 2,150,000 2,150,000 2,150,000 2,150,000 2,650,000
Traffic Signal Rehabilitation II*: 100425 Citywide 10,072,070 2,900,000 1,400,000 1,400,000 1,400,000 1,400,000 1,400,000 19,972,070
Traffic Signal Retiming II: 100522 Citywide 2,451,794 400,000 813,000 150,000 630,000 630,000 150,000 5,224,794
* Project partially State/Federal Funded **Project 100% State/Federal Funded ***Project Also Includes Non-Programmed Funds
9
Projects | Programs with Modifications
Project Council
District
Appropriations
to Date FY26 Budget FY27-31 Budget Total Balance to
Complete
Cleveland Street Phase IV: 100123*4 39,592,807 1,280,183 16,464,661 57,337,651 -
Indian River Road Safety Improvements: 100660 2 1,500,000 -9,181,617 10,681,617 18,436,348
Indian River Road Phase VII-A: 100217*1,2,7 60,529,770 --60,529,770 35,427,777
Indian River Road Phase VII-B: 100213*1,2,7 14,114,886 --14,114,886 9,510,223
Rosemont Road Phase V: 100340*10 24,535,228 1,000,000 -25,535,228 17,019,809
Traffic Safety Improvements IV (TSI): 100423*Citywide 27,362,365 7,330,218 31,189,826 65,882,409 -
* Project partially State/Federal Funded **Project 100% State/Federal Funded ***Project Also Includes Non-Programmed Funds
10
100123: Cleveland Street Improvements IV Council
District(s):
4
Total Project
Cost
$57.3 M
•Proposed to receive $14,545,807 from 100048 Burton
Station Road Improvements II
•First appeared in the FY 2012-13 CIP.
•Provides funding for design, property acquisition,
and construction of an improved Cleveland
Street/Columbus Street.
•The new road will feature a 3-lane, 79-foot-wide
roadway that will run 1.2 miles in length between
Witchduck Road and Independence Boulevard.
•The project also includes replacement of traffic
signals at Dorset Avenue and Kellam Road, turn
lanes, shared-use pathways, on-road bike lanes, on-
street parking, and landscaping.
Appropriations to Date FY26 Budget FY27-31 Budget Total Balance to
Complete
39,592,807 1,280,183 16,464,661 57,337,651 -11
100660: Indian River Road
Safety Improvements
Council
District(s):
2
Total Project
Cost
$29.1 M
•Proposed increase of $9,181,617 in Year 2 (FY27)
•Funded by the Major Projects Fund
•This project first appeared in the FY 2023-24 CIP.
•This project will provide safety improvements along
Indian River Road between West Neck Road and
Princess Anne Road.
•The safety improvements will include shoulder
widening, raising the road to reduce recurring
flooding, increase lane widths, relocate overhead
utilities, and other geometric improvements.
•The project will be evaluated for phased
implementation depending on the final scope of
the improvements.
Appropriations to Date FY26 Budget FY27-31 Budget Total Balance to
Complete
1,500,000 -9,181,617 10,681,617 18,436,348 12
100217: Indian River Road Phase VII-A &
100213: Indian River Road Phase VII-B
Council
District(s):
1,2,7
Total Project
Cost
$119.6 M
•Programmed funds removed from projects & redistributed,
re-scoping options being assessed
•The overall Indian River Road Phase VII project first appeared in
the FY 1995-96 CIP.
•Ultimate construction of a four-lane divided roadway
configuration on Indian River Road from Lynnhaven Parkway to
Elbow Road, a distance of approximately 2.1 miles.
•Phase VII-A will provide two through lanes (southbound)
•Phase VII-B will provide two through lanes (northbound)
•The typical roadway section includes multi-use paths, on-road
bicycle accommodations, streetlights, landscaping, and noise
barriers
Project Appropriations to Date FY26 Budget FY27-31 Budget Total Balance to
Complete
Phase VII-A 60,529,770 --60,529,770 35,427,777
Phase VII-B 14,114,886 --14,114,886 9,510,223
Total 74,644,656 --74,644,656 44,938,000 13
100340: Rosemont Road Phase V Council
District(s):
10
Total Project
Cost
$42.6 M
•Programmed funds removed from project &
redistributed, re-scoping options being assessed
•This project first appeared in the FY 2013-14 CIP.
•This project is for the construction of a four-lane
divided roadway from Primrose Lane/Harbinger Road
to Dam Neck Road, a distance of approximately 1.3
miles.
•Project will include a continuous 10-foot-wide
sidewalk along the east side of the corridor as well as
a 10-foot-wide sidewalk along the west side from
Faculty Boulevard to Lynnhaven Parkway.
•This project also includes the upgrade of three
existing traffic signals at Buckner Boulevard, Faculty
Boulevard/Celtic Drive, and Concert Drive.
Appropriations to Date FY26 Budget FY27-31 Budget Total Balance to
Complete
24,535,228 1,000,000 -25,535,228 17,019,809 14
100423: Traffic Safety Improvements Phase IV (TSI)Council
District(s):
Citywide
•Yearly allocation increased due to expected speed camera
revenue
•This program focuses on smaller roadway safety improvements
including: turn lanes, sidewalks, signals, bike/ped
improvements, and visual obstructions
•Primary source of City match funds for smaller state/federal
grant projects (costs have also increased)
•Cost increases have reduced the effectiveness of this program
Appropriations
to Date FY26 FY27 FY28 FY29 FY30 FY31 Total Balance to
Complete
27,362,365 7,330,218 7,331,005 6,665,541 6,165,541 5,862,198 5,165,541 65,882,409 -15
New Projects | Programs
Project Council
District
Appropriations to
Date FY26 Budget FY27-31 Budget Total Balance to
Complete
Transportation Network Analysis : 100429 Citywide -250,000 -250,000 -
Virginia Beach Blvd & Independence Blvd
Ped Crossings: 100692**4,8 1,000,000 1,000,000 1,023,734 3,023,734 -
* Project partially State/Federal Funded **Project 100% State/Federal Funded ***Project Also Includes Non-Programmed Funds
16
100429: Transportation Network Analysis Council
District(s):
Citywide
•Used to perform analyses of transportation network
and system needs and costs, including:
•Transportation & traffic modeling
•Development of roadway alignments
•Cost estimates
•Detailed scoping
•Roadway location
•Typical section
•Corridor accident and congestion studies,
•Design criteria
•Special features such as aesthetics
•Funded by VDOT Maintenance funds
Appropriations to Date FY26 Budget FY27-31 Budget Total Balance to
Complete
-250,000 -250,000 -17
100692: Virginia Beach Blvd &
Independence Blvd Ped Crossings
Council
District(s):
4, 8
Total Project
Cost
$3 M
•Includes installing signalized pedestrian crossings,
installing high-visibility backplates, and
associated improvements at 12 existing signalized
intersections:
•9 existing, signalized intersections along
Virginia Beach Boulevard
•3 existing, signalized intersections along
Independence Boulevard
•The project will improve pedestrian safety along
the Virginia Beach Blvd and Independence Blvd
corridors.
Appropriations to Date FY26 Budget FY27-31 Budget Total Balance to
Complete
1,000,000 1,000,000 1,023,734 3,023,734 -18
Projects | Programs Complete & Removed
Project Council
District
Total Project
Cost Status
Independence Blvd / Columbus Street Pedestrian Imp.: 100554*4 562,385 Complete
Laskin Road Bridge Replacement*** (VDOT Managed)6 86,253,363 Complete
Laskin Road Phase I-A*** (VDOT Managed)6 56,190,962 Complete
Sandbridge Road - Nimmo VII-A*2, 5 26,890,707 Complete
Various Cost Participation Projects II: 100447 Citywide 350,000 Complete
Wetlands Mitigation Banking II: 100484 Citywide 300,000 Complete
Centerville Turnpike Phase III: 100058*7 93,348,275 Removed
Ferrell Parkway: 100171 1, 7 9,675,456 Removed
Indian River Rd / Princess Anne Rd Intersection Imp: 100329 2 11,236,391 Removed
Princess Anne Road Phase VII-A: 100317 2 17,539,832 Removed
* Project partially State/Federal Funded **Project 100% State/Federal Funded ***Project Also Includes Non-Programmed Funds
19
Requested but Not Funded
20
Project Existing/New Council District Total
Neighborhood Sidewalk Program New Citywide 3,000,000 ($500K/Yr)
Elbow Road Phase II-D: 100160*Existing 2 45,220,928
Holland Road Phase I: 100564*Existing 3, 10 4,095,294
Independence Blvd/Edwin Drive Intersection*Existing 3 3,746,099
Landstown Road Phase I: 100235 Existing 2 24,326,360
Laskin Road Phase I-B: 100239*Existing 6 33,213,779
Laskin Road Phase II: 100501*Existing 6 20,468,296
Laskin Road Phase III: 100243**Existing 6 18,337,330
Nimmo Parkway Phase VII-B: 100278*Existing 2, 5 20,744,835
Pacific Avenue Turn Lanes: 100673*Existing 5, 6 29,864,643
Pleasure House Road Phase I: 100524 Existing 9 16,620,854
Pleasure House Road Phase II: 100306 Existing 9 23,008,646
Shore Drive Phase IV: 100383*Existing 9 71,366,422
Woodstock Road Sidewalk Existing 1 2,850,125
Projects Underway & Completed
▪Construction started in FY25:
▪Atlantic Ave Pedestrian Improvements
▪Elbow Road Phase II-B & II-C
▪Shore Drive Phase III (May 1, 2025)
▪Construction completed in FY25:
▪Bus Shelter Improvements Phase 5 & 7 (3 new shelters)
▪Euclid Rd Sidewalk Phase 1
▪Independence Blvd/Columbus St Pedestrian Improvements
▪Laskin Rd Bridge Replacement/Laskin Rd Phase 1-A (VDOT)
▪Sandbridge Rd—Nimmo Pkwy Phase 7A
▪South Blvd Sidewalk Phase 2
21
Elbow Road Phase II-B & II-C at the North
Landing River crossing (looking east)
Major Challenges
Market Conditions
•Regional construction activity continues to put pressure on
the market
•Fewer bidders, higher prices, continued labor market
shortages
Inflation/Cost Increases
•Cost increases have moderated (2-4%), some material lead
times have improved
State/Federal Funding
•Some uncertainty with federal grant funds—no fiscal
impacts yet
•City has been transparent with VDOT about making strategic
funding cuts
•Phase funding versus full project funding is only a short-term
solution 22
Major Challenges Continued
Programmatic Items
•CIP programming continues to be challenging due to cost
increases. Overall cost increase by Fiscal Year:
$171M FY24
$121M FY25
$216.2M FY26 ($119M cost increases, $97.2M inflation)
•Total BTC has grown to $567M - includes $256M of
state/federal projects that should be fully funded
Other Issues
•Tariff impacts—monitor and track for now
•Federally funded projects already have Buy America
requirements, no major impacts from tariffs are anticipated
at this time
23