ECONOMIC & TOURISMCAPITAL IMPROVEMENT PROGRAM
Emily Archer, Deputy Director
Economic Development
April 29, 2025
Economic and Tourism Section Overview
•FY 2025-26 Proposed CIP -33 projects totaling
$532.6million including appropriations to date
•Funding Sources
•General Fund (20%)
•Cigarette Tax Dedication
•Sale of Property
•Tourism Investment Program (63%)
•Federal and State Grants
•Parking Enterprise Fund
•Town Center SSD
•Lease and Sale of Properties (BRAC)
2
Major Challenges
•Inflationary Challenges
•Construction cost increase
•Labor and Material shortages
•Decrease in some revenues
•Cigarette Tax
3
Projects with No Change
4
Project Council
District
Appropriations
to Date FY26 Budget FY27-31
Budget Total Balance to
Complete
100002: 17th St Improvements Ph II 6 293,630 0 0 293,630 76,813,199
100014: APZ-1 Economic Incentives Citywide 1,857,692 0 0 1,857,692 -
100635: Corporate Landing
Business Park Infrastructure
5 10,000,000 0 0 10,000,000 -
100666: Dam Neck Road-London
Bridge Connector Improvements
5 22,500,000 0 0 22,500,000 -
100157: Economic Development
Investment Program II
Citywide 12,075,696 1,295,986 5,463,465 18,835,147 -
100251: London Bridge Commerce
Center Infrastructure
6 1,730,762 0 0 1,730,762 2,164,338
100262: Lynnhaven Parkway
Corridor Improvements
3 7,939,338 0 0 7,939,338 -
Projects with No Change – Continued
5
Project Council
District
Appropriations
to Date FY26 Budget FY27-31
Budget Total Balance to
Complete
100399: Strategic Development
Projects
Citywide 11,945,687 250,000 1,250,000 13,445,687 -
100577: Strategic Site Acquisition
and Disposition
Citywide 1,690,000 0 0 1,690,000 -
100576: VA Beach Innovation
Park Infrastructure II
2 18,659,000 0 0 18,659,000 -
100459 ViBe District Street
Infrastructure Improvements
6 10,811,046 0 0 10,811,046 -
Total 107,762,302
Projects with No Change – TIP Funded4
6
Project Council
District
Appropriations
to Date
FY26
Budget
FY27-31
Budget Total
100001: 17th St Improvements Ph I 6, 5 48,843,040 0 0 48,843,040
100145: Atlantic Park Development
Acquisition
6 9,194,182 0 0 9,194,482
100146: Atlantic Park
Entertainment Venue
6 54,997,614 0 0 54,997,614
100147: Atlantic Park Parking 6 45,950,000 0 0 45,950,000
100148: Atlantic Park Streetscapes 6 6,000,000 0 0 6,000,000
100283: Oceanfront Capital
Projects Reinvestment
6, 5 7,331,862 600,000 3,000,000 10,931,862
100300: Atlantic Avenue Street
Improvements
6, 5 33,900,000 7,900,000 6,300,000 48,100,000
100456: VA Beach Amphitheater
Capital Maintenance
2 4,241,446 200,000 1,000,000 5,441,446
Projects with No Change – TIP Funded Continued 24
7
Project Council
District
Appropriatio
ns to Date FY26 Budget FY27-31
Budget Total
100489: Winston Salem Avenue
Improvements
5 18,558,235 0 0 18,558,235
100606: Atlantic Park Offsite
Structure
6 36,567,955 0 0 36,567,955
100628: Visitor Information
Services
6, 5 1,000,000 0 0 1,000,000
100629: Sports Tourism
Infrastructure
Citywide 19,500,000 0 0 19,500,000
100286: Oceanfront Restrooms 6, 5 2,833,484 0 0 2,833,484
100059: Resort Parking District 6, 5 26,125,000 0 0 26,125,000
Total 334,043,118
Projects with No Change-Partial Federal/State Funded
8
Project Council
District
Appropriations
to Date
FY26
Budget
FY27-31
Budget Total
100282: Oceana & ITA Conformity
& Acquisition II
2, 6, 5, 3 8,642,318 0 5,000,000 13,642,318
100630: 17th St Regional
Stormwater Management Facility
6 28,700,000 0 0 28,700,000
100639: Cape Henry Lighthouse
Restoration
6 1,918,119 0 0 1,918,119
Total 44,260,437
Projects with No Change - SSD Funded
9
Project Council
District
Appropriations
to Date
FY26
Budget
FY27-31
Budget Total
100420: Town Center Garage and
Plaza Capital Maintenance II
4 4,180,127 325,726 1,763,630 6,296,483
100421: Town Center Reinvestment 4 1,050,000 150,000 750,000 1,950,000
Total 8,246,483
Projects with Modifications
Project Council
District
Appropriations
to Date FY26 Budget FY27-31
Budget Total Balance to
Complete
100285: Oceanfront Parking
Facilities Capital Maintenance
Development II
6, 5 5,853,366 612,500 3,062,500 9,528,366 -
100048: Burton Station Road
Improvements III
4 3,065,658 0 0 3,065,658 24,918,922
Total 5,853,366 9,528,366
▪$14,545,807 proposed to be transferred to Roadway project 100123 “Cleveland Street
Improvements IV”
10
New Project – Pembroke Square Public Parking
Project Council
District
Appropriations
to Date FY26 Budget FY27-31 Budget Total
100686: Pembroke Square
Public Parking
9 0 25,680,150 0 25,680,150
Total 0 25,680,150 0 25,680,150
▪Debt service to be repaid through dedication of taxes generated
11
Requested But Not Funded
Project Existing/New Council
District Total
Burton Station Road Improvements III Additional Funding Existing 4 24,918,922
VA Beach Innovation Park Infrastructure III Existing 2 7,000,000
Corporate Landing Business Park Infrastructure Phase II Existing 5 13,000,000
Total 44,918,922
▪Current Phase Construction Underway
in both Business Parks
▪Innovation Park complete in 2025
▪Corporate Landing complete in 2026
12
100300: Atlantic Avenue Street Improvements
▪Task Force established to determine a path
forward at $35 Mil or less by the end of 2025
Council District Appropriations to
Date FY26 Budget FY27-31
Budget Total
6, 5 33,900,000 7,900,000 6,300,000 48,100,000
13
Projects Recently Completed – 31st St Canopy 2
14
Before
Projects Recently Completed – 31st St Canopy 2
15
After
Projects Recently Completed – 18th Street2
16
Before
Projects Recently Completed – 18th Street2
17
After
Projects Underway
▪Atlantic Park
▪Dam Neck Road-London Bridge Connector
▪Innovation Park Infrastructure
▪Corporate Landing Infrastructure
▪Winston Salem Improvements
▪Lynnhaven Parkway Improvements
▪17th Street Phase 1 Improvements
18