HomeMy WebLinkAboutCentral Resort District Drainage Improvements Engineering Report 05272025Central Resort District Drainage Improvements
Preliminary Engineering Report
City Council Update
Mike Tippin, PE | May 27, 2025
Agenda
2
Background
Selected Alternative
Project Phasing
Summary and Costs
There are no decisions to be made today
the intent of this presentation is to inform
City Council and the public.
Background
3
Central Resort District CIP
Project Area
21st St Pacific AveArctic Ave24th St
19th St Baltic Ave17th St
4
Central Resort District Drainage
Improvements (CIP: 100062)
• New stormwater pipes, tide
gate, pump stations, storage,
and ocean outfall
24th St Culvert (CIP: 100061)
• Replace small pipe with large
box culvert
• Improve conveyance at Old
Virginia Beach Road and
Parks Avenue
21st St and Baltic Ave Drainage
Improvements (CIP: 100275)
• Redirects stormwater to
reduce flooding at 21st St and
Baltic
1
2
3
1
2
3
Development History
5
1937 1958
Development History
6
1974 2024
Flooding – Rainfall Events
7
August 11, 2022
21st Street
August 28, 2023
Flooding – Rainfall Events
24th Street Culvert
25th Street (Baltic/Med)
8
Flooding – Tidal Events
Holly Road
Arctic/Baltic/Beach Garden Park
9
Recurrent Flooding
21st StreetHurricane Sandy
21st Half Street and Baltic Ave Baltic Ave and 29th Street
10
Previous Studies
11
12
Design Criteria
100-year Level of Service
Passable Roadways, Visible Crown
Fully Contained in Storm System
Critical Infrastructure
Sea Level Rise
Meet PW Design Standard to the maximum extent practicable
100-yr
10-yr
No SLR 100-yr*
1.5 ft
10-yr
25-yr
50-yr
3 ft
25-yr
50-yr
* Assume future flood gates installed at Lesner Bridge and
Rudee Inlet, remove SLR for 100-yr checkstorms
3 ft SLR
21st & 22nd Streets (I-264)
VB Convention CenterVB Convention Center
Pacific Ave & Laskin RdPacific Ave & Laskin Rd
7.2 ft tailwater in Lower Little Neck Creek
4.3
4.7
5.4
5.4
7.2
7.2
Design Tailwater
Draft PER Alternatives Overview
VB Visitor
Center
MOCA
MOCA/Parks Ave
Old Beach Park
Beach Garden Park 24th St
Park
27th St
Laskin Rd
Tide Gate
Project Area
21st St Pacific AveArctic Ave24th St
19th St Baltic Ave17th St
13
•Holistic Approach utilizing
the same criteria as
Stormwater Master Plans
•7 Alternatives Evaluated
•Focused on City-Owned
Parcels
•Outfalls
•Atlantic Ocean
•Little Neck Creek
Selected Alternative
14
Ultimate Improvements
•Laskin Road Culverts and
Tide Gates
•Parks Ave Pump Station
•24th Street Culvert
•24th Street Microtunneling
•24th Street Park Pump Station
•Channel Improvements
(MOCA)
•Other improvements
•Storm system upgrades
15
Laskin Road Culverts
16
Laskin Road Tide Gate
•Automatic tide gate on the north
side of Laskin Road
•Existing double 6’x6’ box culvert
•Gate OPENS:
Water elevation in Beach Garden Park ≥ Tailwater
•Gate CLOSES:
Tailwater ≥ 1.5 ft
Allows for normal ebb and flow of ~ 60% of higher high
tides
17
Parks Ave Pump Station
220 CFS CAPACITY
Two (2) 60 cfs pumps
One (1) 100 cfs pump
18
Parks Ave Pump Station
19
24th Street Microtunneling
21
22
Laydown Area and Bore Pit
(mostly in 24th Street)
Laydown Area and Bore Pit
(mostly in 24th Street)
23
Captures Existing
Storm Pipes
Proposed Triple 78”
Culverts in 24th Street
Microtunneling
Machine
Captures Existing
Storm Pipes
Proposed Triple 78”
Culverts in 24th Street
Microtunneling
Machine
24
25
“And all this
happening below
a fully functional
road…”
“And all this
happening below
a fully functional
road…”
26
950 CFS CAPACITY
Two (2) 100 cfs pumps
Three (3) 250 cfs pumps
24th Street Park Pump Station – Ocean Outfall
24th Street Park – Alternative 1
28
29
Pump Control House,
Visitor Center, and
Park Facilities
Generator
House
Generator
House
30
Ocean Outfalls –
Horizontal Direction Drill
Ocean Outfalls –
Horizontal Direction Drill
Below Grade
Wet Well
Below Grade
Wet Well
Triple 78”
Culverts
Triple 78”
Culverts
24th Street Culvert
•Raise 24th Street to elevation 7.5
•Replace Existing 54-inch Culvert With 35’x6’
opening 31
24th Street Culvert
32
MOCA Existing Channel
33
MOCA Proposed
34
Project Phasing
35
Ultimate Program Improvements
Estimated Construction Cost $386,200,000
36
Phase 1A – Laskin Road Culverts and Tide Gates
37
•Double capacity of Laskin Road culverts
•Automatic Tide Gate on Laskin Road Culverts
Improvements
Estimated
Construction Cost
$8,900,000
Phase 1A – Laskin Road Culverts and Tide Gates
38
•Immediate, noticeable relief from dry weather tidal
nuisance flooding at low-lying areas near Beach
Garden Park
•Kilbourne Ct, Holly Rd, 28th Street area
Structure
Flooding
# of Buildings
Street Flooding
Miles of RoadPhase
100-yr 10-yr100-yr10-yr
46410.641.031A
Flood ReliefFlood Relief
100-yr Flood Reduction
Phase 1B – Parks Ave Pump Station
Improvements
•Parks Ave Pump Station (260 cfs)
•Full size for Ultimate build-out
•72-inch pipe on 23rd Street
•Pipe improvements on Baltic &
Arctic Ave between 21st & 23rd
39
Estimated
Construction Cost
$66,400,000
Phase 1B – Parks Ave Pump Station
40
Structure
Flooding
# of Buildings
Street Flooding
Miles of RoadPhase
100-yr 10-yr100-yr10-yr
46410.641.031A
26450.640.651B
72861.281.68TOTAL
Flood ReliefFlood Relief
•Contains 10-yr storm at 21st & Baltic Ave, 21st &
Arctic Ave
100-yr Flood Reduction
Phase 2A – 24
th Street Microtunneling
Improvements
•Microtunnel triple 78-inch trunk line on 24
th Street
•Pipe improvements on Baltic & Arctic between 23rd & 24th
•Connections on Pacific, north Arctic, north Baltic, and north Mediterranean
inactive until later phases
•Drains to Parks Ave pump station via backflow
•Storage in system above -4 ft
41
Estimated
Construction Cost
$102,300,000
Phase 2A – 24
th Street Microtunneling
Flood ReliefFlood Relief
100-yr Flood Reduction
•Contains 10-yr storm on Baltic & Arctic south of
24th Street
Significant cost savings if constructed at the same time as Phase 2B
42
Structure
Flooding
# of Buildings
Street Flooding
Miles of RoadPhase
100-yr 10-yr100-yr10-yr
46410.641.031A
26450.640.651B
350.210.122A
75911.491.80TOTAL
Phase 2B – 24
th Street Pump Station
Improvements
•24th Street Park pump station (950 cfs) & ocean outfall
•Below-grade pump station
•24th Street Park improvements
•Bathroom facilities, information kiosk, stage, other amenities
•Activate connections to side street systems installed in Phase 2A
•Add final connections on Atlantic Ave
43
Estimated
Construction Cost
$119,800,000
Phase 2B – 24
th Street Pump Station
Flood ReliefFlood Relief
•Achieves passable road conditions on Baltic &
Arctic between 21st & 24th Streets during 100-year
storm
•Water quality TMDL benefit from redirecting
significant area away from the Chesapeake Bay
100-yr Flood Reduction
44
Structure
Flooding
# of Buildings
Street Flooding
Miles of RoadPhase
100-yr 10-yr100-yr10-yr
46410.641.031A
26450.640.651B
350.210.122A
6981.210.362B
144992.702.16TOTAL
Phase 3 – Arctic Avenue North
Improvements
•78-inch trunkline on Arctic Ave
between 24th & 28th Street
•Automatic weir gate on existing twin
90-inch outfall to Beach Garden Park
•Prevent unwanted drawdown of BGP
by the 24th Street pump station during
dry weather
•Misc. pipe capacity improvements
45
Estimated
Construction Cost
$22,700,000
Phase 3 – Arctic Ave North
Flood ReliefFlood Relief
•Allows Beach Garden Park to be drawn down by
24th Street Park pump station
•Brings flood relief to 28th Street area
•Expands passable road conditions during 100-yr
storm
100-yr Flood Reduction
46
Structure
Flooding
# of Buildings
Street Flooding
Miles of RoadPhase
100-yr 10-yr100-yr10-yr
46410.641.031A
26450.640.651B
350.210.122A
6981.210.362B
46460.970.683
1901453.672.84TOTAL
Phase 4 – Parks Ave and Cypress Ave
Improvements
•Parks Ave pipe improvements to 19th
Street
•Cypress Ave pipe improvements
47
Estimated
Construction Cost
$26,200,000
Phase 4 – Parks Ave and Cypress Ave
Flood ReliefFlood Relief
•Creates passable roadways during 100-yr storm
for critical infrastructure, 21st & 22nd Streets
•Reduces flooding on 19th Street
•Takes east branch of MOCA channel offline
100-yr Flood Reduction
48
Structure
Flooding
# of Buildings
Street Flooding
Miles of RoadPhase
100-yr 10-yr100-yr10-yr
46410.641.031A
26450.640.651B
350.210.122A
6981.210.362B
46460.970.683
3260.850.504
2221514.523.34TOTAL
Phase 5 – 24
th Street and MOCA Channel
Improvements
•Remove Old Virginia Beach Rd
entrance to MOCA
•Channel & floodplain improvements
•Neighborhood pipe upgrades
•Raise 24th Street to crown elevation
7.5 ft
•24th Street culvert replacement with
35’x6’ opening
•Additional culverts under I-264
49
Estimated
Construction Cost
$20,600,000
Phase 5 – 24
th Street and MOCA Channel
Flood ReliefFlood Relief
•Brings flood relief to Convention Center area
•Reduces flooding in neighborhood west of MOCA
•Channel & floodplain improvements increase
storage capacity
100-yr Flood Reduction
50
Structure
Flooding
# of Buildings
Street Flooding
Miles of RoadPhase
100-yr 10-yr100-yr10-yr
46410.641.031A
26450.640.651B
350.210.122A
6981.210.362B
46460.970.683
3260.850.504
840.160.275
2301554.683.61TOTAL
Phase 6 – Parks Ave and Mediterranean Ave
51
Improvements
•Additional pipe improvements on
Parks Ave south of 19th Street
•Mediterranean Ave pipe
improvements
Estimated
Construction Cost
$19,300,000
Inset A Inset B
Phase 6 – Parks Ave and Mediterranean Ave
52
Flood ReliefFlood Relief
•Allows Virginia Beach Blvd to contain 10-year storm
after redevelopment of trailer park
•Reduces flooding near Mediterranean & 25th Street
100-yr Flood Reduction
Structure
Flooding
# of Buildings
Street Flooding
Miles of RoadPhase
100-yr 10-yr100-yr10-yr
46410.641.031A
26450.640.651B
350.210.122A
6981.210.362B
46460.970.683
3260.850.504
840.160.275
020.090.076
2301574.773.68TOTAL
Summary and Costs
53
10-year, with
1.5 ft SLR
Flooding
54
Laskin Road Culverts
and Tide Gates
Parks Avenue
Pump Station
24th Street
Microtunneling
24th Street Pump
Station
Arctic Avenue NorthParks Avenue and
Cypress Avenue
24th Street and MOCA
Channel
Parks Avenue and
Mediterranean Avenue
10-yr Flood Reduction
55
Existing 10-yr Flood
Baltic AveMed Ave22nd St
Arctic AvePacific Ave19th St
100-year Flooding
Laskin Road Culverts
and Tide Gates
Parks Avenue
Pump Station
24th Street
Microtunneling
24th Street Pump
Station
Arctic Avenue NorthParks Avenue and
Cypress Avenue
24th Street and MOCA
Channel
Parks Avenue and
Mediterranean Avenue
100-yr Flood ReductionExisting 100-yr Flood
Baltic AveMed Ave22nd St
Arctic AvePacific Ave19th St
57Baltic AveMed Ave22nd St Pacific Ave19th St
Estimated Construction Cost
58
Estimated Total Project Cost: $577,000,000
Estimated
Construction
Cost with
Escalation
Escalation
5% / YR
Estimated
Construction
Cost
Stormwater Improvement ProjectsPhase
$10.3 M$1.4 M$8.9 MLaskin Road Culverts and Tide Gates1A
$83.4 M$17.0 M$66.4 MParks Ave Pump Station1B
$135.6 M$33.3 M$102.3 M24thStreet Microtunneling2A
$171.3 M$51.5 M$119.8 M24thStreet Pump Station2B
$34.5 M$11.8 M$22.7 MArctic Avenue North3
$39.6 M$13.4 M$26.2 MParks Avenue and Cypress Avenue4
$31.9 M$11.3 M$20.6 M24thStreet and MOCA Channel5
$31.2 M$11.9 M$19.3 MParks Avenue and Mediterranean Avenue6
$537.8 M$151.6 M$386.2 MTOTAL:
Summary
59
Estimated Total Project Cost: $577,000,000
Structure
Flooding
(100-yr Storm)
Street
Flooding
(10-yr Storm)
Estimated
Construction
Cost w/
Escalation
(Cumulative)
Stormwater Improvement Projects
(Cumulative)Phase
5166.05 mi$0Current Conditions (No Improvements)
4705.02 mi$10.3 MLaskin Road Culverts and Tide Gates1A
4444.37 mi$93.7 MParks Ave Pump Station1B
4414.25 mi$229.3 M24thStreet Microtunneling2A
3723.89 mi$400.6 M24thStreet Pump Station2B
3263.21 mi$435.1 MArctic Avenue North3
2942.71 mi$474.7 MParks Avenue and Cypress Avenue4
2862.44 mi$506.6 M24thStreet and MOCA Channel5
2862.37 mi$537.8 MParks Avenue and Mediterranean Avenue6
Schedule
60
Q4 2029
Q4 2029
TBD
TBD
TBD
TBD
TBD
TBD
Q4 2027
Q4 2027
TBD
TBD
TBD
TBD
TBD
TBD
Q4 2026
Q4 2026
TBD
TBD
TBD
TBD
TBD
TBD
Q2 2026
Q2 2026
TBD
TBD
TBD
TBD
TBD
TBD
Pre-Final
Pre-Final
Pre-Final
Pre-Final
Pre-Final
Pre-Final
Pre-Final
Pre-Final
PH 1A – Laskin Rd Culverts and Tide Gates
PH 1B – Parks Ave Pump Station
PH 2A – 24
th St Microtunneling
PH 2B – 24
th St Pump Station w/ Ocean Outfall
PH 3 – Arctic Ave North Storm Imp
PH 4 – Parks Ave and Cypress Ave Storm Imp
PH 5 – 24
th Street and MOCA Channel
PH 6 – Parks Ave and Med Ave Storm Imp
Preliminary
Engineering
Construction
Start
RFQ / RFP
Interviews
Design Build
Team Selected
Construction
Complete
Summary
With NO Infrastructure Improvements, modeling results:
•6.05 miles of roadways flood during a 10-year design storm
(3 inches or more over crown)*
•516 structures flood during a 100-year design storm
WITH Infrastructure Improvements, modeling results:
•61% Decrease in Street Flooding (from 6.05 miles to 2.37 miles)
•45% Decrease in Structure Flooding (from 516 to 286)
Questions?
Thank You.