HomeMy WebLinkAbout06032025 Rudee CC Discussion_Direction PARRUDEE PARK MASTER PLAN
Follow-up Briefing
Michael Kirschman, Parks and Recreation Director
Chad Morris, Planning Design & Development Administrator
June 3, 2025
1
AGENDA
Seeking City Council Direction
•Overall Park Design
•Opinion of Probable Cost/Budget
•Parking
•Surface Parking or Parking Garage
•Currently Leased Parking Spaces and Agreements
•Sponsorships
•Next Steps
•Timeline
•Discussion and Guidance
2
PARK DESIGN
RUDEE PARK PROJECT
3
VIBRANT OCEANFRONT DESTINATION
VIBRANT OCEANFRONT DESTINATION
4
FROM LOOP
5
SHARED USE PATH
JETTY WALK
TO DESTINATION OCEANFRONT PARK
6
BEACH VILLAGE & WATER PLAZA
BEACH VILLAGE & WATER PLAZA
OCEAN OVERLOOK
WATER PLAZA
WAVE OVERLOOK
INLET STEPS
SHARED USE PATH BEACH VILLAGE
7
WAVE OVERLOOK
8
VIEW FROM BEACH OVERLOOK
9
INLET STEPS & WATER PLAZA
INLET STEPS & WATER PLAZA
INLET STEPS
WATER PLAZA
SHARED USE PATH
OCEAN GATEWAY
INLET LOOKOUT
PICNIC GROVE
10
WATER PLAZA
11
INLET STEPS
12
LAWNS, NATURE PLAY, & PAVILION
LAWNS, NATURE PLAY, & PAVILION
PICNIC GROVE
NATURE PLAY
COMMUNITY LAWN
SHARED USE PATH
SUNSET LAWN
PARK PAVILION
13
SHARED USE PATH
14
PICNIC GROVE
15
RUDEE PARK BIRDS EYE
16
OPINION OF PROBABLE
COST/BUDGET
RUDEE PARK PROJECT
17
PARK WITH PARKING GARAGE
PARKING GARAGE
(includes 350 spaces and an allowance for retail &rooftop)
$22,600,000
PARK CONSTRUCTION
(includes roadway and park)
$30,332,000
CONTINGENCY
(10% of construction at 15% design)
$5,293,200
ESCALATION
(10% of construction, 2026/2027)
$5,293,200
FULL TIME 3RD PARTY CITY INSPECTOR
(construction phase on-site field office)
$1,440,000
SOFT COSTS
(design & construction phase fees & services)
$4,500,000
FURNITURE, FIXTURES AND EQUIPMENT
(allowance)
$1,000,000
TOTAL $70,458,400
PARK WITH SURFACE PARKING
PARK CONSTRUCTION
(includes roadway, park & 3rd street surface parking)
$30,807,000
CONTINGENCY
(10% of construction at 15% design)
$3,080,700
ESCALATION
(10% of construction, 2026/2027)
$3,080,700
FULL TIME 3RD PARTY CITY INSPECTOR
(construction phase on-site field office)
$720,000
SOFT COSTS
(design & construction phase fees & services)
$3,950,000
FURNITURE, FIXTURES AND EQUIPMENT
(allowance)
$1,000,000
TOTAL $42,638,400
18
SURFACE PARKING OR PARKING
GARAGE
RUDEE PARK PROJECT
19
PARKING
SURFACE AND GARAGE PARKING
530 SPACES (350 STRUCTURED)
SURFACE PARKING ONLY
437 SPACES
20
ONSITE AND OFFSITE PARKING ANALYSIS
21
PARKING STRUCTURE, RETAIL, ROOF TERRACES
22
PARKING STRUCTURE, RETAIL, ROOF TERRACES
COMMUNITY LAWN
PARKING STRUCTURE
SHARED USE PATH
SUNSET LAWN
PARK PAVILION
NATURE PLAY
PARKING LEASE AGREEMENTS
•Schooner Inn
•2nd Street & Atlantic Avenue
•0.34 acres
•40 parking spaces
•Began in May 2022 with (4) successive renewal options
•Waterman’s
•400 Atlantic Avenue & 205 4th Street
•0.4 acres
•Approx. 41 parking spaces (valet parking)
•Began in August 2022 with (4) successive renewal options
•Dolphin Run Condos
•3rd Street & Atlantic Avenue
•0.09 acres
•Approx. 10 parking spaces
•Began in May 2022 with (4) successive renewal options
23
PARKING LEASE AGREEMENTS
Schooner Inn
Parking Lease Area
40 spaces
Waterman’s
Parking Lease Area
41 spaces
Dolphin Run Condos
Parking Lease Area
10 spaces
24
POTENTIAL PROJECT
DONOR/SPONSORSHIP
OPPORTUNITIES
RUDEE PARK PROJECT
25
PARTICIPATION OPPORTUNITIES
•Naming Rights
•Signature Park Features & Elements
•Sponsorships
•Events, Features, Programming
•Donation
•Public Spaces & Access, Philanthropy, Legacy
•In-Kind Donation
•Construction & Operations Related Industries
26
NATURE PLAY PAVILION INLET STEPS WATER PLAZA BEACH VILLAGE
OCEAN OVERLOOKS
JETTY WALK – COMMUNITY LAWN – SUNSET LAWN - FISHING PLATFORMS - OVERLOOKS … AND MORE
NAMING RIGHTS, SPONSORSHIPS & DONATIONS
DIRECTED TO PARK FEATURES & PROGRAMS
27
Programming and Revenue ($1.5-2M/yr.)
Events & Series
•Concerts, Movie Nights
•Farmers Market
•Winter Village
Food & Beverage
•3-4 Locations
•Kiosks, Restaurant
•Vendor Events
Rental & Activation
•Event Pavilion
•Parties, Corporate Events
•Daily Use – Yoga, Education Games
28
Visitation and Operations ($1.5M/yr.)
Projections
•2-3 Million Annual
Visitors
•Safe, Secure, & Well-
Maintained
•Diversity of Year-Round
Programming
•Promotion, Logistics,
Equipment & Staff
29
VBDA AND CITY PARCELS
RUDEE PARK PROJECT
30
Private Parcels
City Parcels – City of Virginia
Beach
City Parcels – Virginia Beach
Development Authority
VBDA AND CITY PARCELS
31
VBDA AND CITY PARCELS
Existing VBDA parcels
CVB property
transfer to VBDA
32
NEXT STEPS
RUDEE PARK PROJECT
33
TIMELINE
•Begin Construction Documents
•15-18 months to complete
•Solidify donor/sponsorship partnerships and agreements
•Create plats to determine final City and VBDA ownership
•Provide Council with various revenue, operational and
governance models
•Develop Council preferred governance framework
•Bidding and Construction
•Bidding and award – (6-9 months)
•Construction – (24 months)
•Implement operations and governance model
34
DISCUSSION AND GUIDANCE
•Approval of Park Design
•Surface Parking Only
•Surface Lot Acreage Transfer to VBDA
•Approval to Seek Philanthropic Donations
35